Docusign Envelope ID: D6C53305-7513-4331-95AB-7279605F17A9 <br />8.0 TASK 8: Bidding & Negotiating <br />8.1 Pre -Bid Meeting: Prepare and lead a pre -bid meeting and prepare meeting notes. <br />8.2 Contractor Questions and Addenda: Respond to Contractors' questions and prepare <br />and certify addendums. <br />8.3 Certified Bid Tabulation: Review and evaluate the bids and certify the bid tabulation. <br />9.0 TASK 9: Construction Services <br />9.1 Pre -Construction Meeting: Prepare for and attend pre -construction meeting prior to <br />commencement of Work. <br />9.2 Construction Engineering Assistance: Provide clarifications and interpretations to <br />project plans and specifications, prepare change orders and work directives, review <br />shop drawings and samples, review project schedule, evaluate substitutes, review <br />contractor's applications for payment and provide recommendation. <br />9.3 Meetings and Site Visits: Prepare for and attend up to four (4) progress meetings, and <br />perform site visits the same day. <br />ESTIMATED SCHEDULE: <br />The Project will be completed under the tentative milestones shown below. This tentative schedule is <br />based on receiving a Notice to Proceed prior to the end of July 2025, and receiving prompt review and <br />approvals from the CITY. <br />ITEM <br />Kickoff Workshop <br />New Well Site Location Selection* <br />New Well Site Survey* <br />50% Design Services <br />50% Design Workshop <br />Test Well & Sampling* <br />Field Work (Geotech & Survey) <br />90% Design Services <br />90% Design Review Workshop <br />Final Detailed Design Services and Permitting* <br />Bidding Phase <br />Construction Phase <br />TENTATIVE DATE <br />August 2025 <br />August 2025 <br />September - October 2025 <br />October 2025 <br />October 2025 <br />November 2025 <br />November 2025 <br />December 2025 <br />December 2025 <br />January — March 2026 <br />March — April 2026 <br />May 2026 — January 2027 <br />*Schedule of these items dependent on Peerless Midwest, Results from Well Testing, and <br />IDEM review timeline. <br />6/30/2025 Commonwealth Engineers Inc. <br />