BID TABULATION
<br />2025 Curb and Sidewalk
<br />Proj 125-001
<br />2025 Curb and Sidewalk
<br />Base Bid
<br />Engineer's Estimate
<br />C&E Excavating
<br />Milestone Contractors
<br />Premium Services
<br />Rieth-Riley
<br />Selge Construction
<br />TX Concrete
<br />Item No.
<br />Line Item
<br />Quantity
<br />Unit
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />1
<br />CONCRETE SIDEWALK, REMOVE
<br />2,783
<br />Sy
<br />$33.99
<br />$94,605.86
<br />$22.50
<br />$62,617.50
<br />$70.00
<br />$194,810.00
<br />$33.50
<br />$93,230.50
<br />$28.66
<br />$79,760.78
<br />$30.50
<br />$84,881.50
<br />$27.00
<br />$75,141.00
<br />2
<br />CONCRETE SIDEWALK, 4-IN
<br />2,783
<br />Sy
<br />$84.27
<br />$234,523.41
<br />$102.00
<br />$283,866.00
<br />$64.00
<br />$178,112.00
<br />$69.50
<br />$193,418.50
<br />$84.50
<br />$235,163.50
<br />$67.55
<br />$187,991.65
<br />$77.00
<br />$214,291.00
<br />3
<br />CONCRETE CURB, REMOVE
<br />2,420
<br />LF
<br />$25.54
<br />$61,795.67
<br />$8.25
<br />$19,965.00
<br />$24.00
<br />$58,080.00
<br />$10.50
<br />$25,410.00
<br />$22.00
<br />$53,240.00
<br />$28.50
<br />$68,970.00
<br />$17.00
<br />$41,140.00
<br />4
<br />CONCRETE CURB, MODIFIED
<br />2,420
<br />LF
<br />$67.84
<br />$164,172.80
<br />$97.00
<br />$234,740.00
<br />$64.00
<br />$154,880.00
<br />$61.50
<br />$148,830.00
<br />$83.25
<br />$201,465.00
<br />$60.20
<br />$145,684.00
<br />$31.00
<br />$75,020.00
<br />5
<br />CONCRETE APPROACH, REMOVE
<br />546
<br />SY
<br />1 $26.13
<br />$14,266.43
<br />$27.00
<br />$14,742.00
<br />$80.00
<br />$43,680.00
<br />$45.00
<br />$24,570.00
<br />$23.30
<br />$12,721.80
<br />$26.50
<br />$14,469.00
<br />$31.00
<br />$16,926.00
<br />6
<br />PCCP FOR APPROACHES, 6-IN
<br />546
<br />Sy
<br />$134.62
<br />$73,502.52
<br />$123.00
<br />$67,158.00
<br />$118.00
<br />$64,428.00
<br />$100.00
<br />$54,600.00
<br />$153.25
<br />$83,674.50
<br />$127.00
<br />$69,342.00
<br />$91.00
<br />$49,686.00
<br />7
<br />CONCRETE CURB RAMP, REMOVE
<br />85
<br />Sy
<br />$74.20
<br />$6,307.00
<br />$23.00
<br />$1,955.00
<br />$164.00
<br />$13,940.00
<br />$43.00
<br />$3,655.00
<br />$180.00
<br />$15,300.00
<br />$27.50
<br />$2,337.50
<br />$29.00
<br />$2,465.00
<br />8
<br />PERPENDICULAR CURB RAMP
<br />85
<br />Sy
<br />$280.90
<br />$23,876.50
<br />$235.00
<br />$19,975.00
<br />$235.00
<br />$19,975.00
<br />$219.00
<br />$18,615.00
<br />$600.00
<br />$51,000.00
<br />$261.00
<br />$22,185.00
<br />$177.00
<br />$15,045.00
<br />9
<br />TOPSOIL AND SEEDING
<br />3,103
<br />Sy
<br />$13.41
<br />$41,608.13
<br />$17.00
<br />$52,751.00
<br />$22.00
<br />$68,266.00
<br />$28.00
<br />$86,884.00
<br />$14.90
<br />$46,234.70
<br />$5.25
<br />$16,290.75
<br />$105.00
<br />$328,650.00
<br />10
<br />TREE, REMOVE, 6-IN
<br />2
<br />EA
<br />$700.00
<br />$1,400.00
<br />$405.00
<br />$810.00
<br />$600.00
<br />$1,200.00
<br />$640.00
<br />$1,280.00
<br />$715.00
<br />$1,430.00
<br />$620.00
<br />$1,240.00
<br />$1,750.00
<br />$3,500.00
<br />11
<br />TREE, REMOVE, 10-IN
<br />13
<br />EA
<br />$1,134.00
<br />$14,742.00
<br />$805.00
<br />$10,465.00
<br />$1,400.00
<br />$18,200.00
<br />$1,494.00
<br />$19,422.00
<br />$1,570.00
<br />$20,410.00
<br />$1,425.00
<br />$18,525.00
<br />$2,375.00
<br />$30,875.00
<br />12
<br />TREE, REMOVE, 30-IN
<br />19
<br />EA
<br />$1,365.00
<br />$25,935.00
<br />$2,450.00
<br />$46,550.00
<br />$2,500.00
<br />$47,500.00
<br />$2,665.00
<br />$50,635.00
<br />$2,730.00
<br />$51,870.00
<br />$2,550.00
<br />$48,450.00
<br />$6,025.00
<br />$114,475.00
<br />13
<br />TREE, REMOVE, 48-IN
<br />6
<br />EA
<br />$1,600.00
<br />$9,600.00
<br />$6,050.00
<br />$36,300.00
<br />$4,000.00
<br />$24,000.00
<br />$4,270.00
<br />$25,620.00
<br />$4,240.00
<br />$25,440.00
<br />$4,075.00
<br />$24,450.00
<br />$9,595.00
<br />$59,370.00
<br />14
<br />STUMP, REMOVE
<br />7
<br />EA
<br />$315.00
<br />$2,205.00
<br />$605.00
<br />$4,235.00
<br />$300.00
<br />$2,100.00
<br />$320.00
<br />$2,240.00
<br />$530.00
<br />$3,710.00
<br />$350.00
<br />$2,450.00
<br />$1,400.00
<br />$9,800.00
<br />15
<br />PLANT, DECIDUOUS TREE, SINGLE STEM. 2-IN TO 2.5-IN
<br />53
<br />EA
<br />$1,100.00
<br />$58,300.00
<br />$800.00
<br />$42,400.00
<br />$795.00
<br />$42,135.00
<br />$850.00
<br />$45,050.00
<br />$795.00
<br />$42,135.00
<br />$795.00
<br />$42,135.00
<br />$1,700.00
<br />$90,100.00
<br />$826,840.32 $898,529.50 $931,306.00 $793,460.00 $923,555.28 $749,401.40 1,126,484.00
<br />Items in yellow are conflicting with each other. The
<br />values are tabulated as provided by the contractor.
<br />Alt 1
<br />Engineer's Estimate
<br />C&E Excavating
<br />Milestone Contractors
<br />Premium Services
<br />Rieth-Riley
<br />Selge Construction
<br />TX Concrete
<br />Item No.
<br />Line Item
<br />Quantity
<br />Unit
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />Unit Price
<br />Cost
<br />1
<br />CONCRETE SIDEWALK, REMOVE
<br />986
<br />Sy
<br />$33.99
<br />$33,518.28
<br />$17.00
<br />$16,762.00
<br />$70.00
<br />$69,020.00
<br />$35.00
<br />$34,510.00
<br />$29.00
<br />$28,594.00
<br />$34.05
<br />$33,573.30
<br />$27.00
<br />$26,622.00
<br />2
<br />CONCRETE SIDEWALK, 4-IN
<br />949
<br />Sy
<br />$84.27
<br />$79,972.23
<br />$102.00
<br />$96,798.00
<br />$64.00
<br />$60,736.00
<br />$70.00
<br />$66,430.00
<br />$84.50
<br />$80,190.50
<br />$63.50
<br />$60,261.50
<br />$77.00
<br />$73,073.00
<br />3
<br />CONCRETE CURB, REMOVE
<br />965
<br />LF
<br />$25.54
<br />$24,641.66
<br />$12.00
<br />$11,580.00
<br />$24.00
<br />$23,160.00
<br />$12.00
<br />$11,580.00
<br />$22.00
<br />$21,230.00
<br />$32.05
<br />$30,928.25
<br />$17.00
<br />$16,405.00
<br />4
<br />CONCRETE CURB, MODIFIED
<br />965
<br />LF
<br />$67.84
<br />$65,465.60
<br />$97.00
<br />$93,605.00
<br />$64.00
<br />$61,760.00
<br />$65.00
<br />$62,725.00
<br />$83.25
<br />$80,336.25
<br />$58.50
<br />$56,452.50
<br />$31.00
<br />$29,915.00
<br />5
<br />CONCRETE APPROACH, REMOVE
<br />116
<br />Sy
<br />$26.13
<br />$3,030.96
<br />$18.00
<br />$2,088.00
<br />$80.00
<br />$9,280.00
<br />$50.00
<br />$5,800.00
<br />$23.30
<br />$2,702.80
<br />$30.05
<br />$3,485.80
<br />$31.00
<br />$3,596.00
<br />6
<br />PCCP FOR APPROACHES, 5-IN
<br />116
<br />Sy
<br />$134.62
<br />$15,615.92
<br />$123.00
<br />$14,268.00
<br />$155.00
<br />$17,980.00
<br />$105.00
<br />$12,180.00
<br />$160.00
<br />$18,560.00
<br />$138.00
<br />$16,008.00
<br />$91.00
<br />$10,556.00
<br />7
<br />CONCRETE CURB RAMP, REMOVE
<br />27
<br />Sy
<br />$74.20
<br />$2,003.40
<br />$29.00
<br />$783.00
<br />$164.00
<br />$4,428.00
<br />$55.00
<br />$1,485.00
<br />$180.00
<br />$4,860.00
<br />$31.05
<br />$838.35
<br />$29.00
<br />$783.00
<br />8
<br />PERPENDICULAR CURB RAMP
<br />27
<br />Sy
<br />$280.90
<br />$7,584.30
<br />$235.00
<br />$6,345.00
<br />$235.00
<br />$6,345.00
<br />$232.00
<br />$6,264.00
<br />$600.00
<br />$16,200.00
<br />$291.00
<br />$7,857.00
<br />$177.00
<br />$4,779.00
<br />9
<br />TOPSOIL AND SEEDING
<br />1,284
<br />Sy
<br />$13.41
<br />$17,217.16
<br />$18.00
<br />$23,112.00
<br />$24.00
<br />$30,816.00
<br />$32.00
<br />$41,088.00
<br />$14.90
<br />$19,131.60
<br />$6.95
<br />$8,923.80
<br />$105.00
<br />$134,820.00
<br />10
<br />TREE, REMOVE, 10-IN
<br />6
<br />EA
<br />$1,134.00
<br />$6,804.00
<br />$805.00
<br />$4,830.00
<br />$1,200.00
<br />$7,200.00
<br />$1,550.00
<br />$9,300.00
<br />$1,520.00
<br />$9,120.00
<br />$1,225.00
<br />$7,350.00
<br />$2,375.00
<br />$14,250.00
<br />11
<br />TREE, REMOVE, 30-IN
<br />6
<br />EA
<br />$1,365.00
<br />$8,190.00
<br />$3,025.00
<br />$18,150.00
<br />$2,500.00
<br />$15,000.00
<br />$3,150.00
<br />$18,900.00
<br />$2,700.00
<br />$16,200.00
<br />$2,550.00
<br />$15,300.00
<br />$6,025.00
<br />$36,150.00
<br />12
<br />STUMP, REMOVE
<br />5
<br />EA
<br />$315.00
<br />$1,575.00
<br />$605.00
<br />$3,025.00
<br />$300.00
<br />$1,500.00
<br />$385.00
<br />$1,925.00
<br />$530.00
<br />$2,650.00
<br />$350.00
<br />$1,750.00
<br />$1,400.00
<br />$7,000.00
<br />13
<br />PLANT, DECIDUOUS TREE, SINGLE STEM. 2-IN TO 2.5-IN
<br />20
<br />1 EA
<br />$1,100.00
<br />$22,000.00
<br />$850.00
<br />$17,000.00
<br />$850.00
<br />$17,000.00
<br />$1,050.00
<br />$21,000.00
<br />$850.00
<br />$17,000.00
<br />$850.00
<br />$17,000.00
<br />$1,700.00
<br />$34,000.00
<br />$287,618.51
<br />$308,346.00
<br />$324,225.00
<br />$293,187.00
<br />$316,775.15
<br />$259,728.50
<br />$391,949.00
<br />S:\Public Works\Projects\Projects by Year\2025 Projects\125-0012025 Curb and Sid ewalk\1-Admin\1- BPW Documents\Bid Tabulation.xlsx
<br />
|