<br />giving the Contractor and the Contractor's surety, if any, seven days' notice, terminate employment of the Contractor and
<br />may, subject to any prior rights of the surety:
<br />.1 Exclude the Contractor from the site and take possession of all materials, equipment, tools, and construction
<br />equipment and machinery thereon owned by the Contractor;
<br />.2 Accept assignment of subcontracts pursuant to Section 5.4; and
<br />.3 Finish the Work by whatever reasonable method the Owner may deem expedient. Upon written request of the
<br />Contractor, the Owner shall furnish to the Contractor a detailed accounting of the costs incurred by the Owner
<br />in finishing the Work.
<br />§ 14.2.3 When the Owner terminates the Contract for one of the reasons stated in Section 14.2.1, the Contractor shall not be
<br />entitled to receive further payment until the Work is finished.
<br />§ 14.2.4 If the unpaid balance of the Contract Sum exceeds costs of finishing the Work, including compensation for the
<br />Architect's services and expenses made necessary thereby, and other damages incurred by the Owner and not expressly
<br />waived, such excess shall be paid to the Contractor. If such costs and damages exceed the unpaid balance, the Contractor
<br />shall pay the difference to the Owner. The amount to be paid to the Contractor or Owner, as the case may be, shall be
<br />certified by the Initial Decision Maker, upon application, and this obligation for payment shall survive termination of the
<br />Contract.
<br />§ 14.3 Suspension by the Owner for Convenience
<br />§ 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in whole or
<br />in part for such period of time as the Owner may determine.
<br />§ 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay,
<br />or interruption under Section 14.3.1. Adjustment of the Contract Sum shall include profit. No adjustment shall be made to the
<br />extent
<br />1 that performance is, was, or would have been, so suspended, delayed, or interrupted, by another cause for which
<br />the Contractor is responsible; or
<br />.2 that an equitable adjustment is made or denied under another provision of the Contract.
<br />§ 14.4 Termination by the Owner for Convenience
<br />§ 14.4.1 The Owner may, at any time, terminate the Contract for the Owner's convenience and without cause.
<br />§ 14.4.2 Upon receipt of notice from the Owner of such termination for the Owner's convenience, the Contractor shall
<br />.1 cease operations as directed by the Owner in the notice;
<br />.2 take actions necessary, or that the Owner may direct, for the protection and preservation of the Work; and
<br />.3 except for Work directed to be performed prior to the effective date of termination stated in the notice, terminate
<br />all existing subcontracts and purchase orders and enter into no further subcontracts and purchase orders.
<br />§ 14.4.3 In case of such termination for the Owner's convenience, the Owner shall pay the Contractor for Work properly
<br />executed; costs incurred by reason of the termination, including costs attributable to termination of Subcontracts; and the
<br />termination fee, if any, set forth in the Agreement.
<br />AIA Document A2019° - 2017. Copyright 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 1
<br />and 2017 by The American Institute of Architects. A11 rights reserved. WARNING: This AIA Document rs protected by U.S. Copyright
<br />Law and International Treaties. Unauthorized reproduction or distribution of this AIAm Document, or any portion of it, may result
<br />in severe civil and c nal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was
<br />produced by AIA softwareat09:02:25 on 0 10/2017 under Order No. 1496524162 which expires on 03/09/2018, and is not for resale.
<br />User Notes: (369ADA17)
<br />
|