AIA Document A2 01- -- 2017 <br />General Conditions of the Contract for Construction <br />§ 9.8 Substantial Completion <br />§ 9.8.1 Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is <br />sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its <br />intended use. <br />§ 9.8.2 When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is <br />substantially complete, the Contractor shall prepare and submit to the Architect a comprehensive list of items to be completed <br />or corrected prior to final payment. Failure to include an item on such list does not alter the responsibility of the Contractor to <br />complete all Work in accordance with the Contract Documents. <br />§ 9.8.3 Upon receipt of the Contractor's list, the Owner or Architect will make an inspection to determine whether the Work <br />or designated portion thereof is substantially complete. If the Owner or Architect's inspection discloses any item, whether or <br />not included on the Contractor's list, which is not sufficiently complete in accordance with the Contract Documents so that <br />the Owner can occupy or utilize the Work or designated portion thereof for its intended use, the Contractor shall, before <br />issuance of the Certificate of Substantial Completion, complete or correct such item upon notification by the Owner or <br />Architect. In such case, the Contractor shall then submit a request for another inspection by the Owner or Architect to <br />determine Substantial Completion. <br />§ 9.8.4 When the Work or designated portion thereof is substantially complete, the Architect will prepare a Certificate of <br />Substantial Completion that shall establish the date of Substantial Completion; establish responsibilities of the Owner and <br />Contractor for security, maintenance, heat, utilities, damage to the Work and insurance; and fix the time within which the <br />Contractor shall finish all items on the list accompanying the Certificate. Warranties required by the Contract Documents <br />shall commence on the date of Substantial Completion of the Work or designated portion thereof unless otherwise provided <br />in the Certificate of Substantial Completion. <br />§ 9.8.5 The Certificate of Substantial Completion shall be submitted to the Owner and Contractor for their written acceptance <br />of responsibilities assigned to them in the Certificate. Upon such acceptance, and consent of surety if any, the Owner shall <br />make payment of retainage applying to the Work or designated portion thereof. Such payment shall be adjusted for Work that <br />is incomplete or not in accordance with the requirements of the Contract Documents. <br />§ 9.9 Partial Occupancy or Use <br />§ 9.9.1 The Owner may occupy or use any completed or partially completed portion of the Work at any stage when such <br />portion is designated by separate agreement with the Contractor, provided such occupancy or use is consented to by the <br />insurer and authorized by public authorities having jurisdiction over the Project. Such partial occupancy or use may <br />commence whether or not the portion is substantially complete, provided the Owner and Contractor have accepted in writing <br />the responsibilities assigned to each of them for payments, retainage, if any, security, maintenance, heat, utilities, damage to <br />the Work and insurance, and have agreed in writing concerning the period for correction of the Work and commencement of <br />warranties required by the Contract Documents. When the Contractor considers a portion substantially complete, the <br />Contractor shall prepare and submit a list to the Architect as provided under Section 9.8.2. Consent of the Contractor to <br />partial occupancy or use shall not be unreasonably withheld. The stage of the progress of the Work shall be determined by <br />written agreement between the Owner and Contractor or, if no agreement is reached, by decision of the Architect. <br />§ 9.9.2 Immediately prior to such partial occupancy or use, the Owner, Contractor, and Architect shall jointly inspect the area <br />to be occupied or portion of the Work to be used in order to determine and record the condition of the Work. <br />§ 9.9.3 Unless otherwise agreed upon, partial occupancy or use of a portion or portions of the Work shall not constitute <br />acceptance of Work not complying with the requirements of the Contract Documents. <br />AIA Document A201" - 2017. Copyright 1911, 1915, 1916, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1967, 1997, 2007 1 <br />and 2017 by The American Institute of Architects. A11 rights reserved. WARNING: This AIA` Document is protected by U.S. Copyright <br />Law and International Treaties, Unauthorized reproduction or distribution of this AIA° Document, or any portion of it, may result <br />ever. civil and criminal penalties, and will be prosecuted to the ma extent possible under the law. This draft was <br />produced by AIA software at 09:02:25 on 05/10/2017 under Order No. 1496524162 which expires on 03/09/2018, and is not for resale. <br />User Notes: (3B9ADA17) <br />