AIA Document A2 01TM - 2017
<br />General Conditions of the Contract for Construction
<br />.1 allowances shall cover the cost to the Contractor of materials and equipment delivered at the site and all
<br />required taxes, less applicable trade discounts;
<br />.2 Contractor's costs for unloading and handling at the site, labor, installation costs, overhead, profit, and other
<br />expenses contemplated for stated allowance amounts shall be included in the Contract Sum but not in the
<br />allowances; and
<br />.3 whenever costs are more than or less than allowances, the Contract Sum shall be adjusted accordingly by
<br />Change Order. The amount of the Change Order shall reflect (1) the difference between actual costs and the
<br />allowances under Section 3.8.2.1 and (2) changes in Contractor's costs under Section 3.8.2.2.
<br />§ 3.8.3 Materials and equipment under an allowance shall be selected by the Owner with reasonable promptness
<br />§ 3.9 Superintendent
<br />§ 3.9.1 The Contractor shall employ a competent superintendent and necessary assistants who shall be in attendance at the
<br />Project site during performance of the Work. The superintendent shall represent the Contractor, and communications given to
<br />the superintendent shall be as binding as if given to the Contractor.
<br />§ 3.9.2 The Contractor, as soon as practicable after award of the Contract, shall notify the Owner and Architect of the name
<br />and qualifications of a proposed superintendent. Within 14 days of receipt of the information, the Architect may notify the
<br />Contractor, stating whether the Owner or the Architect (1) has reasonable objection to the proposed superintendent or (2)
<br />requires additional time for review. Failure of the Architect to provide notice within the 14-day period shall constitute notice
<br />of no reasonable objection.
<br />§ 3.9.3 The Contractor shall not employ a proposed superintendent to whom the Owner or Architect has made reasonable and
<br />timely objection. The Contractor shall not change the superintendent without the Owner's consent, which shall not
<br />unreasonably be withheld or delayed.
<br />§ 3.10 Contractor's Construction and Submittal Schedules
<br />§ 3.10.1 The Contractor, promptly after being awarded the Contract, shall submit for the Owner's and Architect's information
<br />a Contractor's construction schedule for the Work. The schedule shall contain detail appropriate for the Project, including (1)
<br />the date of commencement of the Work, interim schedule milestone dates, and the date of Substantial Completion; (2) an
<br />apportionment of the Work by construction activity; and (3) the time required for completion of each portion of the Work.
<br />The schedule shall provide for the orderly progression of the Work to completion and shall not exceed time limits current
<br />under the Contract Documents. The schedule shall be revised at appropriate intervals as required by the conditions of the
<br />Work and Project.
<br />§ 3.10.2 The Contractor, promptly after being awarded the Contract and thereafter as necessary to maintain a current submittal
<br />schedule, shall submit a submittal schedule for the Architect's approval. The Architect's approval shall not be unreasonably
<br />delayed or withheld. The submittal schedule shall (1) be coordinated with the Contractor's construction schedule, and (2)
<br />allow the Architect reasonable time to review submittals. If the Contractor fails to submit a submittal schedule, or fails to
<br />provide submittals in accordance with the approved submittal schedule, the Contractor shall not he entitled to any increase in
<br />Contract Sum or extension of Contract Time based on the time required for review of submittals.
<br />§ 3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to the Owner
<br />and Architect.
<br />§ 3.11 Documents and Samples at the Site
<br />The Contractor shall make available, at the Project site, the Contract Documents, including Change Orders, Construction
<br />Change Directives, and other Modifications, in good order and marked currently to indicate field changes and selections
<br />made during construction, and the approved Shop Drawings, Product Data, Samples, and similar required submittals. These
<br />AIA Document A201n' - 2017. Copyright 1911, 1915, 1916, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 1
<br />and 2 01 7 by The American Institute of Architects. A11 rights reserved. WARNING: This AIA` Document is protected by U.5_ Copyright
<br />Law and International Treaties, Unauthorized reproduction or distribution of this AIA° Document, or any portion of it, may result
<br />in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was