DATE: <br />PROJECT NO: <br />CITY OF SOUTH BEND <br />DEPARTMENT OF PUBLIC WORKS <br />PROJECT CHANGE ORDER <br />Oct. 22, 2024 121-048B <br />PROJECT NAME: N eigborhood Improvements-Longfellow and South <br />CONTRACT DATE: Mar 09, 2023 <br />CHANGE ORDER NO. 2 <br />SUBJECT OF CHANGE ORDER: Final Quantity Adjustment <br />All items completed substantially as planned. <br />See attached Comparison of Estimate for overruns and underruns. <br />The original contract sum <br />Net change by previously authorized change orders <br />The contract sum prior to this change order <br />By this Change Order, the project amount is <br />The new contract sum including this change order <br />This Change Order represents a total change of <br />Total change for entire project <br />Original contracted completion date/time <br />Extension of date/time by previous change orders <br />Date/time extension by this change order <br />New completion date/time <br />CONTRACTOR <br />2 Contractor Signature O.tt<L ���t" f111 /rs h� <br />Printed Name and Title <br />�-"-R-f -�t C--ct.,,L, G, ,::,._Company name .. <br />Address <br />�()J(-r)uJ J:lJ 4 (l It{ <br />City, State, Zip <br />$ 441,412.71 $ 72,000.00 <br />$ 513,412.71 <br />1:8] Increased D Decreased $ 7,747.28 <br />$ 521,159.99 <br />1.51 <br />18.07 <br />9/15/2023 <br />76 Days <br />0 <br />11/30/2023 <br />RECOMMENDED FOR APPROVAL <br />��� <br />President <br />Member <br />Member <br />Member <br />Member <br />CITY OF SOUTH BEND <br />BOARD OF PUBLIC WORKS <br />Approved Date: __ <br />% <br />% <br />October 22, 2024