ITEMDESCRIPTIONORIG BID QTY.UNITS UNIT PRICE TOTALC.O. #1 ADJUSTED QTY.REVISED TOTAL COST AFTER C.O. #1Cost Difference% of orig contract0.2 GENERAL CONDITIONS 1 LS 63,123.50$ 1$ 151,992.25$ 88,868.75$ 241%0.4 OWNER'S CONTINGENCY1LS100,000.00$ 1$ -$ (100,000.00)$ 0%1FULL DEPTH SLAB REPAIR@ BEAM /GIRDER304 SF $ 87.00 26,448.00$ 524$ 45,588.00$ 19,140.00$ 172%2 FULL DEPTH SLAB REPAIR - FORMED1146 SF $ 97.00 111,162.00$ 4,396$ 426,412.00$ 315,250.00$ 384%5 CONCRETE JOIST SPALL REPAIR200LF $ 115.00 23,000.00$ 500$ 57,500.00$ 34,500.00$ 250%6 BEAM /GIRDER SPALL REPAIR150SF $ 116.00 17,400.00$ 400$ 46,400.00$ 29,000.00$ 267%8 GALVANIC ANODES INSTALLED200 EA $ 65.00 13,000.00$ 500$ 32,500.00$ 19,500.00$ 250%ALT 3 LEVEL 7 PLAZA PAVER INSTALLATION 4,470 SF1LS164,220.00$ 1$ 10,000.00$ (154,220.00)$ 6%TOTAL CONTRACT AMOUNT1,170,220.00$ 1,422,258.75$ 122%ADDITIONAL PAINTING COST (wash down entire garage, paint all columns, walls up to 2, addtn'l ceiling peeled)LS $ 1 Scope Addition 1 $ 108,650.00 FLOOR DRAIN REPLACEMENTEA $ 4,800.00 Unforeseen 6 $ 28,800.00 CONCRETE TESTINGLS $ 9,250.00 Unforeseen 1 $ 9,250.00 GRAND TOTAL WITH PROPOSED EXTRAS1,568,958.75$ 398,738.75$ 134.1%Net change after using Owner's ContingencyUnforeseen Conditions <br />123-054R Liberty Tower TIF Project - Change Order No. 1