Laserfiche WebLink
�iA�, NATIONAL POWER RODDING <br />Wr A Carylon Company <br />July 9, 2024 <br />City of South Bend <br />227 W Jefferson Blvd. <br />South Bend, IN 46601 <br />RE: Sewer and Manhole Rehabilitation, Project No. 122-019- Work Plan <br />2500 West Arthington Street <br />Chicago, IL 60612 <br />p: (312) 666-7700 <br />f: (312) 666-0748 <br />www.nationalpowerrodding.com <br />National Power Rodding plans to have two pre -cleaning and televising crews to work on this <br />project. We estimate 30 working days to complete the pre -clean and TV. <br />National Power Rodding will start the CIPP lining after cleaning and TV crews have worked for <br />at least three weeks onsite. CIPP lining is estimated at 35 working days to complete and <br />manhole to manhole CIPP work within two lining crews. <br />National Power Rodding will start the manhole rehabilitation as the last phase of the work and <br />estimate 60 working days to complete this project with two crews onsite. <br />National Power Rodding plans the over all completion of this project to be 4 to 6 months weather <br />permitting. <br />