								    substance of any direct communications between the Owner and the Construction Manager otherwise relating to the 
<br />Project. Communications by and with the Architect's consultants shall be through the Architect. 
<br />§ 5.14 The Owner shall coordinate the Architect's duties and responsibilities set forth in the Agreement between the 
<br />Owner and the Construction Manager with the Architect's services set forth in this Agreement. The Owner shall 
<br />provide the Architect a copy of the executed agreement between the Owner and Construction Manager, including 
<br />the General Conditions of the Contract for Construction. 
<br />§ 5.15 The Owner shall provide the Architect access to the Project site prior to commencement of the Work and shall 
<br />obligate the Construction Manager to provide the Architect access to the Work wherever it is in preparation or 
<br />progress. 
<br />§ 5.16 Within 15 days after receipt of a written request from the Architect, the Owner shall furnish the requested 
<br />information as necessary and relevant for the Architect to evaluate, give notice of, or enforce lien rights. 
<br />ARTICLE 6 COST OF THE WORK 
<br />§ 6.1 For purposes of this Agreement, the Cost of the Work shall be the total cost to the Owner to construct all 
<br />elements of the Project designed or specified by the Architect and shall include the Construction Manager's general 
<br />conditions costs, overhead, and profit. The Cost of the Work also includes the reasonable value of labor, materials, 
<br />and equipment, donated to, or otherwise furnished by, the Owner. The Cost of the Work does not include the 
<br />compensation of the Architect; the compensation of the Construction Manager for Preconstruction Phase services; 
<br />the costs of the land, rights -of -way, financing, or contingencies for changes in the Work; or other costs that are the 
<br />responsibility of the Owner. 
<br />§ 6.2 The Owner's budget for the Cost of the Work is provided in the Initial Information, and shall be adjusted 
<br />throughout the Project as required under Sections 5.3 and 6.4. Evaluations of the Owner's budget for the Cost of the 
<br />Work represent the Architect's judgment as a design professional. 
<br />§ 6.3 The Owner shall require the Construction Manager to include appropriate contingencies for design, bidding or 
<br />negotiating, price escalation, and market conditions in estimates of the Cost of the Work. The Architect shall be 
<br />entitled to rely on the accuracy and completeness of estimates of the Cost of the Work the Construction Manager 
<br />prepares as the Architect progresses with its Basic Services. The Architect shall prepare, as an Additional Service, 
<br />revisions to the Drawings, Specifications or other documents required due to the Construction Manager's 
<br />inaccuracies or incompleteness in preparing cost estimates, or due to market conditions the Architect could not 
<br />reasonably anticipate. The Architect may review the Construction Manager's estimates solely for the Architect's 
<br />guidance in completion of its services, however, the Architect shall report to the Owner any material inaccuracies 
<br />and inconsistencies noted during any such review. 
<br />§ 6.3.1 If the Architect is providing cost estimating services as a Supplemental Service, and a discrepancy exists 
<br />between the Construction Manager's cost estimates and the Architect's cost estimates, the Architect and the 
<br />Construction Manager shall work together to reconcile the cost estimates. 
<br />§ 6.4 If, prior to the conclusion of the Design Development Phase, the Construction Manager's estimate of the Cost 
<br />of the Work exceeds the Owner's budget for the Cost of the Work, the Architect, in consultation with the 
<br />Construction Manager, shall make appropriate recommendations to the Owner to adjust the Project's size, quality or 
<br />budget for the Cost of the Work, and the Owner shall cooperate with the Architect in making such adjustments. 
<br />§ 6.51f the Construction Manager's estimate of the Cost of the Work at the conclusion of the Design Development 
<br />Phase exceeds the Owner's budget for the Cost of the Work, the Owner shall 
<br />.1 give written approval of an increase in the budget for the Cost of the Work; 
<br />.2 terminate in accordance with Section 9.5; 
<br />.3 in consultation with the Architect and Construction Manager, revise the Project program, scope, or 
<br />quality as required to reduce the Cost of the Work; or 
<br />.4 implement any other mutually acceptable alternative. 
<br />§ 6.6 If the Owner chooses to proceed under Section 6.5.3, the Architect, without additional compensation, shall 
<br />incorporate the revisions in the Construction Documents Phase as necessary to comply with the Owner's budget for 
<br />Init. AIA Document B133-2019.Copyrght®2014, and 2019. Ali rights reserved, the American manse of Amhronn "American lnstowe ofArchltecb;'AIA; the 
<br />AIA Logo, and 'AA contract OocumenW are tndemerlra of T0a American Institute of Architects, 'This documentwas pmtluceel at 11 38:41 ET on 06130W23 12 
<br />under Order No.2114444656 which expires on 0713112024, is not for made, Is licensed for onegme use only and may only be used in acmMance with theAA 
<br />/ Contract Occumentse Terms of service. To report copyright violations, e-mail docinfcl@eiaconbacte.com. 
<br />their Notes: (3119AOA46) 
<br />
								 |