BOWEN <br />30 Providers shall demonstrate their understanding of the Project. <br />3d) Providers are required to detail their plan to construct the Project. This plan shall include <br />construction approach for components such as, but not limited to: equipment, structure, and <br />material procurement; utility coordination and acquisition of temporary electrical power; <br />site dewatering; demolition; excavation means and methods; combined sewer flow bypass <br />plan that maintains flow to the WWTP (<77 MGD) and allows for appropriate combined <br />sewer overflows (>77 MGD); structure and piping construction sequence; equipment <br />installation; startup and testing; paving; and site restoration. <br />3e) Providers shall provide their approach to minimize the construction timeline and submit a <br />construction schedule. The construction must be completed by the City's Long Term Control <br />Plan compliance deadline of December of 2025. The system must be operational by this <br />deadline. <br />