Responses to Questions received July 6, 2023: <br />1. Pay item #10 is "Remove Water Structure." <br />a. Can you clarify what this is referring to? The plans show to remove and relocate <br />1 EA fire hydrant, and remove and dispose of existing water main, assumed to be paid <br />under pay items #29 and #9, respectively. <br />ANSWER: Item 10 is a duplicate and has been removed from the Bid/Proposal form. <br />Attached please find revised form. <br />Is pressure and bac-t testing required on the water main/hydrant relocation portion of <br />the project? <br />ANSWER: Yes. <br />3. If there is a poured thrust block at the back of the existing hydrant that is to be <br />relocated, are we to remove and dispose of this, or leave in place and bury? <br />ANSWER: Remove and dispose. <br />4. It is not anticipated that dewatering will be necessary, if so it will be paid under the bid <br />allowance, correct? <br />ANSWER: Correct. <br />The existing aggregate at the sidewalk area in front of the building can be reused as the <br />agg base as shown on the plan details 12/C3.0 and 11/0.0. <br />ANSWER: This is correct. The Contractor must still ensure that compaction <br />requirements from Specifications are met. <br />Version 8/11/2020 <br />