1 Common Excavation 446 CYS $25.00 $11,150.00 $98.00 $43,708.00 $82.87 $36,960.02
<br />2 Concrete, Remove 198 SYS $14.00 $2,772.00 $19.00 $3,762.00 $38.10 $7,543.80
<br />3 Subgrade Treatment Type II 865 SYS $14.00 $12,110.00 $15.00 $12,975.00 $21.03 $18,190.95
<br />4 Compacted No. 53 Subbase 270 TON $29.00 $7,830.00 $44.00 $11,880.00 $61.92 $16,718.40
<br />5 Milling, 1.5 in.3208 SYS $5.00 $16,040.00 $5.20 $16,681.60 $4.04 $12,960.32
<br />6 HMA Surface, PG64-28P, Type B 321 TON $115.00 $36,915.00 $174.00 $55,854.00 $145.55 $46,721.55
<br />7 HMA Intermediate, Type B 94 TON $115.00 $10,810.00 $187.00 $17,578.00 $309.17 $29,061.98
<br />8 HMA Base, Type B 220 TON $130.00 $28,600.00 $130.00 $28,600.00 $190.28 $41,861.60
<br />9 Tack Coat 2 TON $500.00 $1,000.00 $1.00 $2.00 $339.14 $678.28
<br />10 Joint Adhesive, Surface 1,216 LFT $2.00 $2,432.00 $1.00 $1,216.00 $2.82 $3,429.12
<br />11 PCCP for Approaches, 6 in.23 SYS $82.00 $1,886.00 $181.00 $4,163.00 $158.83 $3,653.09
<br />12 Sidewalk, Concrete 28 SYS $108.00 $3,024.00 $133.00 $3,724.00 $121.41 $3,399.48
<br />13 Curb, Concrete 766 LFT $48.00 $36,768.00 $41.00 $31,406.00 $98.72 $75,619.52
<br />14 Drywell, 3600 gal. Capacity 2 EA $6,289.00 $12,578.00 $11,000.00 $22,000.00 $11,197.49 $22,394.98
<br />15 Curb Ramp, Concrete 29 SYS $280.00 $8,120.00 $265.00 $7,685.00 $359.79 $10,433.91
<br />16 Sodding, Nursery 434 SYS $9.00 $3,906.00 $34.91 $15,150.94 $19.53 $8,476.02
<br />17 Tree, Remove, 30 in.2 EA $1,700.00 $3,400.00 $1,250.00 $2,500.00 $7,756.73 $15,513.46
<br />18 Tree Planting 9 EA $1,700.00 $15,300.00 $648.00 $5,832.00 $1,018.72 $9,168.48
<br />19 Adjust Casting to Grade 5 EA $888.00 $4,440.00 $1,520.00 $7,600.00 $723.21 $3,616.05
<br />20 Adjust Water Valve Casting to Grade 2 EA $686.00 $1,372.00 $175.00 $350.00 $301.34 $602.68
<br />21 Curb Box, Adjust to Grade 9 EA $600.00 $5,400.00 $875.00 $7,875.00 $1,638.42 $14,745.78
<br />22 Fire Hydrant Assembly, Relocate 1 EA $1,500.00 $1,500.00 $7,200.00 $7,200.00 $7,186.34 $7,186.34
<br />23 Sheet Sign with Legend 0.080 in.25 SFT $18.00 $450.00 $63.50 $1,587.50 $24.30 $607.50
<br />24 Sheet Sign, Remove 3 EA $34.00 $102.00 $158.00 $474.00 $386.91 $1,160.73
<br />25 Line, Thermoplastic, Solid, Yellow, 4 in.1,640 LFT $1.00 $1,640.00 $0.88 $1,443.20 $0.91 $1,492.40
<br />26 Line, Thermoplastic, Solid, White, 4 in.2,208 LFT $1.00 $2,208.00 $0.88 $1,943.04 $0.91 $2,009.28
<br />27 Line, Thermoplastic, Broken, Yellow, 4 in.410 LFT $1.00 $410.00 $0.93 $381.30 $0.96 $393.60
<br />28 Line, Thermoplastic, Dotted, Yellow, 4 IN., 2 FT. Line, 4 FT. Gap 30 LFT $2.00 $60.00 $1.66 $49.80 $1.72 $51.60
<br />29 Line, Thermoplastic, Dotted, White, 4 IN., 2 FT. Line, 4 FT. Gap 30 LFT $2.50 $75.00 $1.66 $49.80 $1.72 $51.60
<br />30 Pavement Message Marking, Thermoplastic, Lane Indication Arrow 4 EA $200.00 $800.00 $165.00 $660.00 $170.65 $682.60
<br />31 Grooving for Pavement Markings 3,482 LFT $1.00 $3,482.00 $0.88 $3,064.16 $0.91 $3,168.62
<br />32 Construction Engineering 1 LS $7,000.00 $7,000.00 $4,600.00 $4,600.00 $4,654.04 $4,654.04
<br />33 Mobilization and Demobilization 1 LS $11,600.00 $11,600.00 $22,000.00 $22,000.00 $22,667.92 $22,667.92
<br />34 Clearing Right of Way 1 LS $4,700.00 $4,700.00 $25,600.00 $25,600.00 $18,696.65 $18,696.65
<br />35 Maintenance of Traffic 1 LS $16,300.00 $16,300.00 $27,754.66 $27,754.66 $24,233.18 $24,233.18
<br />36 Erosion Control 1 LS $2,400.00 $2,400.00 $650.00 $650.00 $2,148.19 $2,148.19
<br />Certified 11/9/2022
<br /> Nitin V. Timble PE, LS Date
<br />$470,953.72$398,000.00
<br />Unit PriceESTIMATED
<br />QUANTITY
<br />Unit Price Extension
<br />Main Street Improvements Between Sherwood Street and Dean Street / SB # 122-045
<br />Bid Tab
<br />Unit PriceITEM
<br />Engineer's Estimate Milestone Contractors North Reith Riley Construction Co.
<br />DESCRIPTION OF ITEM UNIT Extension Extension
<br />$278,580.00TOTAL BID (Items 1 to 36)
|