Laserfiche WebLink
CITY OF SOUTH BEND <br />DEPARTMENT OF PUBLIC WORKS <br />PROJECT CHANGE ORDER <br />DATE: 9/16/2022 <br />PROJECT NO: 121-029A <br />PROJECT NAME: Morris Performing Arts Center – Main Level Slab Replacement <br />CONTRACT DATE: <br />CHANGE ORDER NO. 2 <br />SUBJECT OF CHANGE ORDER: Increase in contract amount due to several items changing <br />contractor’s scope of work. <br />All items completed substantially as planned. <br />See attached Comparison of Estimate for overruns and underruns. <br />The original contract sum $ 876,374.83 <br />Net change by previously authorized change orders $ -1,319.00 <br />The contract sum prior to this change order $ 875,055.83 <br />By this Change Order, the project amount is Increased <br /> Decreased $ 91,451.49 <br />The new contract sum including this change order $ 962,982.46 <br />This Change Order represents a total change of 10 % <br />Total change for entire project 9.9 % <br />Original contracted completion date/time 09/23/2022 <br />Extension of date/time by previous change orders <br />Date/time extension by this change order <br />New completion date/time <br />RECOMMENDED FOR APPROVAL <br />CONTRACTOR Construction Manager <br />CITY OF SOUTH BEND <br />BOARD OF PUBLIC WORKS <br />Approved Date: Contractor Signature <br /> <br />Printed Name and Title <br /> <br />President <br />Company name <br /> <br />Member <br />Address <br /> <br />Member <br />City, State, Zip Member <br />Member <br />Darin Meyer- Project Manager <br />Larson Danielson Construction <br />302 Tyler Street <br />La Porte, IN, 46350 <br />October 11, 2022