BID/PROPOSAL
<br />CITY OF SOUTH BEND
<br />Project Name: 2022 Community Crossing Road Rehabilitation Project
<br />Project Number: 122-024R
<br />For Bids Due: August 4, 2022
<br />Contractor Name: Rieth-Riley Construction Co., Inc.
<br />DIVISION 2A - SOUTHLEA DRIVE BASE BID (FROM LILAC DR. TO EASTMONT DR.)
<br />Item
<br />No.
<br />Description
<br />Quantity
<br />Unit
<br />Unit Price
<br />Total Amount
<br />1
<br />Common Excavation
<br />1096
<br />CYS
<br />$ 50.0
<br />$ 54,800.0
<br />2
<br />Concrete, Remove
<br />4063
<br />SYS
<br />$ 20.0
<br />$ 81,260.0
<br />3
<br />Subgrade Treatment Type II (Undistributed)
<br />1317
<br />SYS
<br />$ 25.0
<br />$ 32,925.0
<br />4
<br />Compacted No. 53 Subbase
<br />1629
<br />TON
<br />$ 38.0
<br />$ 61,902.0
<br />5
<br />Sidewalk, Concrete
<br />354
<br />SYS
<br />$ 170.00
<br />$ 60,180.0
<br />6
<br />Curb Ramp, Concrete
<br />135
<br />SYS
<br />$ 300.00
<br />$ 40,500.0
<br />7
<br />Milling, Concrete, 2"
<br />22
<br />SYS
<br />$ 160.00
<br />$ 3,520.0
<br />Mid ng, 4 in
<br />SYS
<br />$
<br />$
<br />9
<br />HMA Surface, 9.5 mm - Type B
<br />335
<br />TON
<br />$ 120.00
<br />$ 40,200.0
<br />10
<br />HMA Intermediate, 12.5 mm - Type B
<br />559
<br />TON
<br />$ 112.00
<br />$ 62,608.0
<br />11
<br />HMA Base, 25.0 mm - Type B
<br />894
<br />TON
<br />$ 95.0
<br />$ 84,930.0
<br />12
<br />Tack Coat
<br />3
<br />TON
<br />$ 1.0
<br />$ 3.0
<br />13
<br />Joint Adhesive, Surface
<br />1366
<br />LFT
<br />$ 1.2
<br />$ 1,639.2
<br />14
<br />PCCP for Approaches, 6 in.
<br />531
<br />SYS
<br />$ 200.0
<br />$ 106,200.0
<br />15
<br />Combined Curb & Gutter, Type A
<br />2710
<br />LFT
<br />$ 42.0
<br />$ 113,820.0
<br />16
<br />Sodding, Nursery
<br />978
<br />SYS
<br />$ 22.9
<br />$ 22,298.4
<br />17
<br />Adjust Manhole Casting to Grade
<br />9
<br />EA
<br />$ 300.00
<br />$ 2,700.0
<br />18
<br />Adjust Water Valve Casting to Grade
<br />5
<br />EA
<br />$ 200.00
<br />$ 1,000.0
<br />19
<br />Furnish and Adjust Casting to Grade
<br />9
<br />EA
<br />$ 1,300.00
<br />$ 11,700.0
<br />20
<br />Fire Hydrant Assembly
<br />1
<br />EA
<br />$14,650.00
<br />$ 14,650.0
<br />21
<br />Water Main Lowering, 6" DI
<br />100
<br />LFT
<br />$ 250.00
<br />$ 25,000.0
<br />22
<br />Mailbox Assembly, Remove & Reset
<br />29
<br />EA
<br />$ 350.00
<br />$ 10,150.0
<br />23
<br />Construction Engineering
<br />1
<br />LS
<br />$10,000.00
<br />$ 10,000.0
<br />24
<br />Mobilization and Demobilization
<br />1
<br />LS
<br />$60,000.00
<br />$ 60,000.0
<br />25
<br />Clearing Right of Way
<br />1
<br />LS
<br />$15,000.00
<br />$ 15,000.0
<br />26
<br />Maintenance of Traffic
<br />1
<br />LS
<br />$30,000.00
<br />$ 30,000.0
<br />27
<br />Erosion Control
<br />1
<br />LS
<br />$ 3,000.00
<br />$ 3,000.0
<br />28
<br />Water Main Line Stop
<br />2
<br />EA
<br />$12,600.00
<br />$ 25,200.0
<br />DIVISION 2A - SOUTHLEA DRIVE BASE BID TOTAL $975,185.60
<br />Version 09/29/2021 Contractor's Bid for Public Works - 8