BID/PROPOSAL
<br />CITY OF SOUTH BENDYS�,ti�,,���
<br />PROJECT NAME: 2021 Drainage Improvements - Kaley St & Marion St
<br />PROJECT NO. 120-006A,`^�,
<br />FOR BIDS DUE: August 24,
<br />2021
<br />CONTRACTOR NAME: Milestone Contractors North, Inc.
<br />DIVISION 2 - MARION STREET IMPROVEMENTS
<br />Item
<br />Description
<br />Quantity
<br />Unit
<br />Unit Price
<br />Total Amount
<br />22
<br />CONSTRUCTION ENGINEERING
<br />1
<br />LSUM
<br />3445.25
<br />$3,445.25
<br />23
<br />MOBILIZATION AND DEMOBILIZATION
<br />1
<br />LSUM
<br />16400.00
<br />$16,400.00
<br />24
<br />MAINTENANCE OF TRAFFIC
<br />1
<br />LSUM
<br />8300.00
<br />$8,300.00
<br />25
<br />VIDEO RECORD
<br />1
<br />LSUM
<br />600.00
<br />$600.00
<br />26
<br />CLEARING OF RIGHT-OF-WAY
<br />1
<br />LSUM
<br />9500.00
<br />$9,500.00
<br />27
<br />TREE REMOVE
<br />3
<br />EACH
<br />850.00
<br />$2,550.00
<br />28
<br />CONCRETE, PAVEMENT REMOVE
<br />40
<br />SYS
<br />36.00
<br />$1,440.00
<br />29
<br />CONCRETE CURB REMOVE
<br />176
<br />LFT
<br />14.00
<br />$2,464.00
<br />30
<br />SURFACE MILLING, ASPHALT 1.5 IN
<br />4900
<br />SFT
<br />1.90
<br />$9,310.00
<br />31
<br />CLEAR AND GRUB
<br />360
<br />SFT
<br />13.00
<br />$4,680.00
<br />32
<br />COMMON EXCAVATION, ASPHALT REMOVE
<br />170
<br />CYS
<br />64.00
<br />$10,880.00
<br />33
<br />STRUCTURAL BACKFILL
<br />75
<br />CYS
<br />0.01
<br />$0.75
<br />34
<br />HMA BASE, TYPE B, 8"
<br />75
<br />TON
<br />150.00
<br />$11,250.00
<br />35
<br />HMA INTERMEDIATE, TYPE B, 2.5"
<br />25
<br />TON
<br />210.00
<br />$5,250.00
<br />36
<br />HMA SURFACE, TYPE B, 1.5"
<br />60
<br />TON
<br />175.00
<br />$10,500.00
<br />37
<br />COMPACTED AGGREGATE, No. 53
<br />25
<br />CYS
<br />60.00
<br />$1,500.00
<br />38
<br />PCCP FOR APPROACH, REINFORCED
<br />40
<br />SYS
<br />255.00
<br />$10,200.00
<br />39
<br />SIDEWALK, CONCRETE, 4 IN
<br />2
<br />SYS
<br />700.00
<br />$1,400.00
<br />40
<br />CURB RAMP, CONCRETE
<br />6
<br />SYS
<br />400.00
<br />$2,400.00
<br />41
<br />CONCRETE CURB
<br />190
<br />LFT
<br />70.00
<br />$13,300.00
<br />42
<br />CURB INLET, 24" DIA
<br />4
<br />EACH
<br />4700.00
<br />$18,800.00
<br />43
<br />CORE & BOOT EXIST STORM STRUCTURE
<br />1
<br />EACH
<br />4700.00
<br />$4,700.00
<br />44
<br />PVC STORM SEWER PIPE, 121N
<br />180
<br />LFT
<br />52.00
<br />$9,360.00
<br />45
<br />RCP STORM SEWER PIPE, 121N
<br />95
<br />LFT
<br />59.00
<br />$5,605.00
<br />46
<br />HYDROMULCH, SEEDING AND TOPSOIL
<br />50
<br />SYS
<br />100.00
<br />$5,000.00
<br />47
<br />OVERSTORY TREE, 2-1/2" CAL
<br />2
<br />EACH
<br />1155.00
<br />$2,310.00
<br />48
<br />TREE WATER BAG
<br />2
<br />EACH
<br />80.00
<br />$160.00
<br />49
<br />THERMOPLASTIC LINE, SOLID WHITE, 4 in.
<br />185
<br />LFT
<br />3.00
<br />$555.00
<br />50
<br />THERMOPLASTIC LINE, SOLID YELLOW, 4 in.
<br />420
<br />LFT
<br />3.00
<br />$1,260.00
<br />Version 01/13/2021 Contractor's Bid for Public Works - 8