Bowen Labor <br />Classification Rate/HR Hours Cost <br />Carpenter 72.66$ 64 4,650.24$ <br />Carpenter Foreman 80.17$ 16 1,282.72$ <br />Supervision LS 24 2,520.00$ <br />Bowen Equipment <br />Classification Rate/Day Days Cost <br />Manlift 225 10 2,250.00$ <br />Total Labor/Equipment Cost 10,702.96$ <br />Bowen Material <br />Classification Rate/Unit Units Needed Cost <br />Sikadur 32 410 4 1,640.00$ <br />Delta Subcontractor <br />Classification Rate/Unit Units Needed Cost <br />Labor LS 23490 23,490.00$ <br />Equipment LS 2960 2,960.00$ <br />Material LS 900 900.00$ <br />Total Material/Sub Cost 28,990.00$