Laserfiche WebLink
Activity ID Activity Name Original <br />Duration <br />Start Finish <br />A1870 Wire Pull 8 - Clean Duct, Rig, and Pull Cable from Power Vault 7 to Colfax Station (Double Circuit)5 12-Oct-21*18-Oct-21 <br />Cable Splicing / Termination / TestingCable Splicing / Termination / Testing 27 18-Oct-21 24-Nov-21 <br />A1900 Terminate Cable at Muessel Substation 2 18-Oct-21*21-Oct-21 <br />A1910 Splice Cable at Power Vault 1 2 21-Oct-21 25-Oct-21 <br />A1920 Splice Cable at Power Vault 2 2 25-Oct-21 27-Oct-21 <br />A1930 Splice Cable at Power Vault 3 2 28-Oct-21 01-Nov-21 <br />A1940 Splice Cable at Power Vault 4 2 01-Nov-21 03-Nov-21 <br />A1950 Splice Cable at Power Vault 5 2 03-Nov-21 08-Nov-21 <br />A1960 Splice Cable at Power Vault 6 2 08-Nov-21 10-Nov-21 <br />A1970 Splice Cable at Power Vault 7 2 10-Nov-21 12-Nov-21 <br />A1990 Terminate Cable at Colfax Substation 3 15-Nov-21 18-Nov-21 <br />A2000 Perform Final Acceptance Testing on (2) Circuits 5 18-Nov-21 24-Nov-21 <br />69kV South Bend T-Line69kV South Bend T-Line 19 18-Oct-21 12-Nov-21 <br />A2490 Install New 69kV Steel Monopole Foundation 4 18-Oct-21*22-Oct-21 <br />A2500 Install New 69kV South Bend Ckt Steel Monopole andf Transfer Conductor 4 22-Oct-21*28-Oct-21 <br />A2510 Wreck out Existing 69kV South Bend Ckt and Structures to Colfax Station 11 28-Oct-21*12-Nov-21 <br />Project Close-OutProject Close-Out 8 29-Nov-21 08-Dec-21 <br />A1880 Complete Final Punchlist / Demobilization 8 29-Nov-21*08-Dec-21 <br />A1890 Project Complete 0 08-Dec-21 <br />Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep <br />Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 <br />Wire Pull 8 - Clean Duct, Rig, and Pull Cable from Power Vault 7 to Colfax Station (Double Circuit) <br />24-Nov-21, Cable Splicing / Termination / Testing <br />Terminate Cable at Muessel Substation <br />Splice Cable at Power Vault 1 <br />Splice Cable at Power Vault 2 <br />Splice Cable at Power Vault 3 <br />Splice Cable at Power Vault 4 <br />Splice Cable at Power Vault 5 <br />Splice Cable at Power Vault 6 <br />Splice Cable at Power Vault 7 <br />Terminate Cable at Colfax Substation <br />Perform Final Acceptance Testing on (2) Circuits <br />12-Nov-21, 69kV South Bend T-Line <br />Install New 69kV Steel Monopole Foundation <br />Install New 69kV South Bend Ckt Steel Monopole andf Transfer Conductor <br />Wreck out Existing 69kV South Bend Ckt and Structures to Colfax Station <br />08-Dec-21, Project Close-Out <br />Complete Final Punchlist / Demobilization <br />Project Complete <br />AEP - Muessel - Colfax Underground (69KV) 5-10's (2) Crews Newkirk Electric Associates Inc.Schedule Date: 04-09-2021 <br />Actual Work <br />Remaining Work <br />Critical Remaining Work <br />Milestone <br />Summary <br />Page 3 of 3 <br />** All start and end dates are subject to applicable approvals and obtaining required permitting. <br />EXHIBIT E - Page 3 of 3