Activity ID Activity Name Original <br />Duration <br />Start Finish <br />AEP - Muessel - Colfax Underground (69KV) 5-10's (2) CrewsAEP - Muessel - Colfax Underground (69KV) 5-10's (2) Crews 164 19-Apr-21 08-Dec-21 <br />Directional Boring (HDD)Directional Boring (HDD)47 30-Apr-21 07-Jul-21 <br />A1115 Directlional Bore #2 Approved 0 30-Apr-21* <br />A1120 Mobilize and Complete East Bank Trail Directional Bore 2 (Station 94+00 to 102+50)20 30-Apr-21*27-May-21 <br />A1125 Michigan/Leeper Bore - Engineering Design Complete / City Approval 0 28-May-21* <br />A2190 Mobilize and Complete HDD Bore Under Michigan St and Leeper Ave - Connect to Vault #5 28 28-May-21*07-Jul-21 <br />Jack and BoreJack and Bore 52 01-Jun-21 12-Aug-21 <br />A2355 Jack and Bore Approved 0 01-Jun-21* <br />A2360 Construct Send and Receive Pits (MOT Map 11)20 01-Jun-21*28-Jun-21 <br />A2370 Mobilize and Complete Jack and Bore Under East Race Canal 15 29-Jun-21*20-Jul-21 <br />A2380 Remove Send and Receive Pits (MOT Map 11)17 21-Jul-21*12-Aug-21 <br />Duct-Bank InstallationDuct-Bank Installation 115 19-Apr-21 28-Sep-21 <br />Phase 4 - West Angela Ave. Crossing Crossing to Wakewa Ave.Phase 4 - West Angela Ave. Crossing Crossing to Wakewa Ave.45 19-Apr-21 18-Jun-21 <br />A1325 Phase 4 - Scope Approved 0 19-Apr-21* <br />A1350 Angela Blvd Crossing - Trench / Install Duct Bank / Backfill Trench (MOT Map 4)5 19-Apr-21*23-Apr-21 <br />A2090 Angela Blvd Crossing - Temporary Asphalt Paving (MOT Map 4)2 26-Apr-21*27-Apr-21 <br />A2100 Angela Blvd Crossing - Sidewalk / Driveway Restoration (MOT Map 4)2 26-Apr-21*27-Apr-21 <br />A2110 EB Trail - Between Angela / Pokagon - Trench / Install Duct Bank / Backfill Trench 7 26-Apr-21*04-May-21 <br />A2120 Pokagon St Crossing - Trench / Install Duct Bank / Backfill Trench (MOT Map 5)4 05-May-21*10-May-21 <br />A2130 Pokagon St Crossing - Sidewalk / Driveway Restoration (MOT Map 5)2 11-May-21*12-May-21 <br />A2150 EB Trail to Michigan St - Trench / Install Duct Bank / Backfill Trench 21 11-May-21*08-Jun-21 <br />A2160 Angela and Pokagon - Mill Temp Asphalt / Final Pave / Stripe (MOT Maps 4,5)3 11-May-21*14-May-21 <br />A2170 EB Trail to Michigan St - Restoration of Trail From Pokagon to Michigan St 8 09-Jun-21*18-Jun-21 <br />A2180 Installation of Power Vault 4 / Associated Fiber Optic Vault 2 09-Jun-21*10-Jun-21 <br />Phase 5 - Wakewa Ave to East North Shore Dr. CrossingPhase 5 - Wakewa Ave to East North Shore Dr. Crossing 30 11-Jun-21 23-Jul-21 <br />A1525 Installation of Power Vault 5 / Associated Fiber Optic Vault 2 11-Jun-21*14-Jun-21 <br />A1530 EB Trail Between Leeper and North Shore Dr - Trench / Install Duct Bank / Backfill Trench 18 15-Jun-21*09-Jul-21 <br />A2200 North Shore Dr and EB Trail Intersection - Trench / Install Duct Bank / Backfill Trench (MOT Map 9)6 12-Jul-21*19-Jul-21 <br />A2210 North Shore Dr and EB Trail Intersection - Sidewalk / Driveway Restoration (MOT Map 9)4 20-Jul-21*23-Jul-21 <br />A2220 North Shore Dr and EB Trail - Restoration of EB Trail and Final Paving of North Shore Dr (MOT Map 9)4 20-Jul-21*23-Jul-21 <br />Phase 6 - East North Shore Dr. Crossing to Crescent Ave.Phase 6 - East North Shore Dr. Crossing to Crescent Ave.36 20-Jul-21 08-Sep-21 <br />A1570 EB Trail South of Dog Park to Crescent Ave - Trench / Install Duct Bank / Backfill Trench 26 20-Jul-21*24-Aug-21 <br />A2240 Installation of Power Vault 6 / Associated Fiber Optic Vault 2 25-Aug-21*26-Aug-21 <br />Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep <br />Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 <br />08-Dec-21, AEP - Muessel - Colfax Underground (69KV) 5-10's (2) Crews <br />07-Jul-21, Directional Boring (HDD) <br />Directlional Bore #2 Approved <br />Mobilize and Complete East Bank Trail Directional Bore 2 (Station 94+00 to 102+50) <br />Michigan/Leeper Bore - Engineering Design Complete / City Approval <br />Mobilize and Complete HDD Bore Under Michigan St and Leeper Ave - Connect to Vault #5 <br />12-Aug-21, Jack and Bore <br />Jack and Bore Approved <br />Construct Send and Receive Pits (MOT Map 11) <br />Mobilize and Complete Jack and Bore Under East Race Canal <br />Remove Send and Receive Pits (MOT Map 11) <br />28-Sep-21, Duct-Bank Installation <br />18-Jun-21, Phase 4 - West Angela Ave. Crossing Crossing to Wakewa Ave. <br />Phase 4 - Scope Approved <br />Angela Blvd Crossing - Trench / Install Duct Bank / Backfill Trench (MOT Map 4) <br />Angela Blvd Crossing - Temporary Asphalt Paving (MOT Map 4) <br />Angela Blvd Crossing - Sidewalk / Driveway Restoration (MOT Map 4) <br />EB Trail - Between Angela / Pokagon - Trench / Install Duct Bank / Backfill Trench <br />Pokagon St Crossing - Trench / Install Duct Bank / Backfill Trench (MOT Map 5) <br />Pokagon St Crossing - Sidewalk / Driveway Restoration (MOT Map 5) <br />EB Trail to Michigan St - Trench / Install Duct Bank / Backfill Trench <br />Angela and Pokagon - Mill Temp Asphalt / Final Pave / Stripe (MOT Maps 4,5) <br />EB Trail to Michigan St - Restoration of Trail From Pokagon to Michigan St <br />Installation of Power Vault 4 / Associated Fiber Optic Vault <br />23-Jul-21, Phase 5 - Wakewa Ave to East North Shore Dr. Crossing <br />Installation of Power Vault 5 / Associated Fiber Optic Vault <br />EB Trail Between Leeper an d North Shore Dr - Trench / Install Duct Bank / Backfill Trench <br />North Shore Dr and EB Trail Intersection - Trench / Install Duct Bank / Backfill Trench (MOT Map 9) <br />North Shore Dr and EB Trail Intersection - Sidewalk / Driveway Restoration (MOT Map 9) <br />North Shore Dr and EB Trail - Restoration of EB Trail and Final Paving of North Shore Dr (MOT Map 9) <br />08-Sep-21, Phase 6 - East North Shore Dr. Crossing to Crescent Ave. <br />EB Trail South of Dog Park to Crescent Ave - Trench / Install Duct Bank / Backfill Trench <br />Installation of Power Vault 6 / Associated Fiber Optic Vault <br />AEP - Muessel - Colfax Underground (69KV) 5-10's (2) Crews Newkirk Electric Associates Inc.Schedule Date: 04-09-2021 <br />Actual Work <br />Remaining Work <br />Critical Remaining Work <br />Milestone <br />Summary <br />Page 1 of 3 <br />EXHIBIT E - Page 1 of 3