BID TABULATION
<br />2020 Community Crossings Round 2
<br />Project No: 120-059
<br />For Bids Due: April 13, 2021
<br />Division 1: Bowman Street (From Miami St. to Leer St.)
<br />Item No.Description Quantity Unit Unit Price Item Total Unit Price Item Total Unit Price Item Total
<br />1 Maintenance of Traffic 1 LS 5,982.69$ 5,982.69$ 10,258.00$ 10,258.00$ 2,890.00$ 2,890.00$
<br />2 Mobilization and Demobilization 1 LS 8,546.70$ 8,546.70$ 4,650.00$ 4,650.00$ 3,000.00$ 3,000.00$
<br />3 Milling, Up to 3"4700 SY 4.00$ 18,800.00$ 2.30$ 10,810.00$ 2.90$ 13,630.00$
<br />4 HMA Surface, 9.5 mm – Type B 780 TONS 65.00$ 50,700.00$ 69.30$ 54,054.00$ 76.00$ 59,280.00$
<br />5 HMA Wedge and Leveling – Type B 39 TONS 60.00$ 2,340.00$ 69.00$ 2,691.00$ 76.00$ 2,964.00$
<br />6 HMA for Patching 9 TONS 120.00$ 1,080.00$ 150.00$ 1,350.00$ 200.00$ 1,800.00$
<br />7 Tack Coat 2 TONS 1.00$ 2.00$ 10.00$ 20.00$ 1.00$ 2.00$
<br />8 Joint Adhesive, Surface 1300 LF 0.60$ 780.00$ 4.00$ 5,200.00$ 0.49$ 637.00$
<br />9 Adjust Manhole to Grade 6 EA 450.00$ 2,700.00$ 200.00$ 1,200.00$ 250.00$ 1,500.00$
<br />10 Adjust Inlet to Grade 10 EA 500.00$ 5,000.00$ 275.00$ 2,750.00$ 250.00$ 2,500.00$
<br />11 Transverse Marking, Thermoplastic, Solid, White, 6"60 SY 2.75$ 165.00$ 6.95$ 417.00$ 6.95$ 417.00$
<br />DIVISION 1 TOTAL 96,096.39$ 93,400.00$ 88,620.00$
<br />Division 2: Ridgedale Road (From York Rd. to Woodmont Dr.)
<br />Item No.Description Quantity Unit Unit Price Item Total Unit Price Item Total Unit Price Item Total
<br />1 Maintenance of Traffic 1 LS 13,325.34$ 13,325.34$ 14,984.00$ 14,984.00$ 2,890.00$ 2,890.00$
<br />2 Mobilization and Demobilization 1 LS 19,036.20$ 19,036.20$ 9,680.00$ 9,680.00$ 3,000.00$ 3,000.00$
<br />3 Milling, Up to 3"11060 SY 4.00$ 44,240.00$ 2.20$ 24,332.00$ 2.90$ 32,074.00$
<br />4 HMA Surface, 9.5 mm – Type B 1820 TONS 65.00$ 118,300.00$ 66.40$ 120,848.00$ 76.00$ 138,320.00$
<br />5 HMA Wedge and Leveling – Type B 91 TONS 60.00$ 5,460.00$ 66.00$ 6,006.00$ 76.00$ 6,916.00$
<br />6 HMA for Patching 22 TONS 120.00$ 2,640.00$ 150.00$ 3,300.00$ 200.00$ 4,400.00$
<br />7 Tack Coat 8 TONS 1.00$ 8.00$ 10.00$ 80.00$ 1.00$ 8.00$
<br />8 Joint Adhesive, Surface 2480 LF 0.60$ 1,488.00$ 4.00$ 9,920.00$ 0.49$ 1,215.20$
<br />9 Adjust Manhole to Grade 9 EA 450.00$ 4,050.00$ 200.00$ 1,800.00$ 250.00$ 2,250.00$
<br />10 Adjust Water Valve Structure to Grade 1 EA 80.00$ 80.00$ 100.00$ 100.00$ 150.00$ 150.00$
<br />11 Adjust Inlet to Grade 10 EA 500.00$ 5,000.00$ 275.00$ 2,750.00$ 250.00$ 2,500.00$
<br />DIVISION 2 TOTAL 213,627.54$ 193,800.00$ 193,723.20$
<br />Rieth-Riley Construction Co.,
<br />Inc.
<br />Rieth-Riley Construction Co.,
<br />Inc.
<br />287,200.00$ 282,343.20$
<br />Engineer's Estimate Milestone Contractors North
<br />Inc
<br />Engineer's Estimate Milestone Contractors North
<br />Inc
<br />DIV. 1 AND 2 TOTAL 309,723.93$