<br />ENGINEER'S ESTIMATE
<br />CITY OF SOUTH BEND
<br />April 17, 2012
<br />Project Name : Main Street/Lafayette Street/La Boulevard Connectgr
<br />Project No.: 11. 0 -058
<br />For Bids Due : 512212012
<br />BASE BID
<br />ITEM N0.
<br />DESCRIPTION
<br />QTY.
<br />UNIT
<br />UNIT PRICE
<br />TOTAL AMOUNT
<br />1
<br />DEWATERING AND PROTECTION OF EXISTING STRUCTURES
<br />1
<br />LS
<br />$5,000.00
<br />$5,000.00
<br />2
<br />CONSTRUCTION ENGINEERING
<br />1
<br />LS
<br />$94,000.00
<br />$94,000.00
<br />3
<br />CPM SCHEDULE
<br />1
<br />LS
<br />$1,250.00
<br />$1,250.00
<br />4
<br />CPM SCHEDULE, MONTHLY UPDATE
<br />13
<br />EA
<br />$200.00
<br />$2,600.00
<br />5
<br />MOBILIZATION AND DEMOBILIZATION
<br />1
<br />LS
<br />$233,000.00
<br />$233,000.00
<br />6
<br />CLEARING RIGHT -OF -WAY
<br />1
<br />LS
<br />$140,000.00
<br />$140,000.00
<br />7
<br />PIPE, REMOVE EXISTING STORM SEWER
<br />73
<br />LFT
<br />$15.00
<br />$1,095.00
<br />8
<br />PIPE, REMOVE EXISTING WATER MAIN
<br />10
<br />LFT
<br />$15.00
<br />$150.00
<br />9
<br />STRUCTURE REMOVE, EXISTING STORM MANHOLE
<br />15
<br />EACH
<br />$1,000.00
<br />$15,000.00
<br />10
<br />STRUCTURE REMOVE, EXISTING SANITARY MANHOLE
<br />2
<br />EACH
<br />$1,200.00
<br />$2,400.00
<br />11
<br />REMOVE, EXISTING CAP, 64NCHES
<br />2
<br />EACH,
<br />$300.00
<br />$600.00
<br />12
<br />REMOVE, EXISTING CAP, 8- INCHES
<br />1
<br />EACH
<br />$350.00
<br />$350.00
<br />13
<br />REMOVE, EXISTING CAP, 10- INCHES
<br />1
<br />EACH
<br />$500.00
<br />$500.00
<br />14
<br />REMOVE, EXISTING FIRE HYDRANT
<br />2
<br />EACH
<br />$1,000.00
<br />$2,000.00
<br />15
<br />ABANDON, EXISTING STORM SEWER
<br />589
<br />LFT
<br />$20.00 $11,780.00
<br />16
<br />ABANDON, EXISTING SANITARY SEWER
<br />680
<br />LFT
<br />$20.00 $13,600.00
<br />17
<br />ABANDON, EXISTING SANITARY MANHOLE
<br />2
<br />EACH
<br />$1,000.00 $2,000.00
<br />18
<br />ABANDON, EXISTING WATER MAIN
<br />485
<br />LFT
<br />$15.00 $7,275.00
<br />19
<br />PAVEMENT REMOVAL
<br />100
<br />SYS
<br />$15.00 $1,500.00
<br />20
<br />COMMON EXCAVATION
<br />35,611
<br />CYS
<br />$8.00 $284,888.00
<br />21
<br />TEMPORARY EROSION AND SEDIMENT CONTROL
<br />1
<br />LS
<br />$37,000.00 $37,000.00
<br />22 COMPACTED
<br />AGGREGATE BASE, NO. 53, BASE
<br />9,130
<br />TON
<br />$21.00 $191,730.00
<br />23 COMPACTED
<br />AGGREGATE BASE, N0, 73, BASE
<br />20
<br />TON
<br />$21.00 $420.00
<br />24 MILLING,
<br />ASPHALT, 1 -112 INCH
<br />176
<br />SYS
<br />$4.00 $704.00
<br />25 HMA
<br />SURFACE, TYPE 8
<br />1,390
<br />TON
<br />$68.00 $94,520.00
<br />26 HMA
<br />INTERMEDIATE, TYPE B
<br />2,280
<br />TON
<br />$64.00 $145,920.00
<br />27 HMA
<br />BASE, TYPE B
<br />7,290
<br />TON
<br />$53.00 $386,370.00
<br />28 HMA
<br />PATCHING, TYPE B
<br />260
<br />TON
<br />$100.00 $26,000.00
<br />29 ASPHALT
<br />FOR TACK COAT
<br />19.5
<br />SYS
<br />$1.00 $19.50
<br />30 PLAIN
<br />CEMENT CONCRETE PAVEMENT PATCH, S- INCHES
<br />92
<br />SYS
<br />$45.00 $4,140.00
<br />Lawson - Fisher Associates P.C.
<br />Project File No 201024.40
<br />April, 2012