Area B (See Appendix A) <br />The following describes the proposed work that Indiana Michigan Power and/or it's <br />subcontractors are to perform in order to re -feed lights and service points in Leeper Park. All <br />work will be done as part of the Bartlett Street Improvements Phase I and Memorial North <br />Parking Lot Project. (City Project No. 114-032 and 114-047). <br />Two 4" conduits (electrical grade) will be installed perpendicularly across Park Lane from the <br />existing I&M Manhole C7-2 to a new above ground Pedestal, see attached photos, that is to be <br />located in Leeper Park approximately 10 to 15ft north of the existing curb. These two conduits <br />will be installed at a minimum burial depth of 36" and they will be concrete encased. The <br />Pedestal that is to be installed is approximately 29" by 16" and it will sit above the ground <br />approximately 24". In addition, we will install underground service wire from this new Pedestal <br />to the existing Pole and H -frame which are within a 15ft radius of the proposed Pedestal <br />location. These underground service conductors will be direct buried at a minimal burial depth <br />of 30". <br />In addition to the primarily underground work described above we will need to do some minor <br />tree trimming on the tree that is located just east and north of the existing I&M Pole. This <br />trimming will be required so that we can re -feed the street lights along Michigan St. with <br />overhead circuitry. <br />For the purposes of screening both the new Pedestal and existing utilities from the general <br />public in the park, a line of six 5 gal. evergreen shrubs (Taxus X Media — see photos) will be <br />placed approximately 5'north of the Pedestal. These shrubs typical grown to 3'-4' in height and <br />are described as an easily maintained hedge. <br />The disturbed area will be restored to its original condition. If any additional soil is required to <br />level out the area after compaction it will be done with topsoil. Once construction is complete, <br />all disturbed areas will be covered with new sod of the same type that is currently on site. <br />