6. NEW (BUSINESS (Cont'd
<br />Motion for the approval of Change Order No. 4 to Rehabilitation
<br />Contract No. 16 was made by Mr. Wiggins, seconded by Mr. Cira.
<br />Mr. Gene Evans, Executive Secretary, Civic Planning Association,
<br />raised the question on having a contract with the original con-
<br />tractor, Ted Combs Decorating & Construction Company, for
<br />$7,722.69, and having a second contractor, Slatile Roofing and
<br />Sheet Metal Company, with the contract price of $1,570.00, on
<br />how that will work out, with reference to the memorandum? Mr.
<br />Crighton advised the contract with Slatile will be deducted
<br />from Ted Combs' contract relative to the items that Slatile is
<br />completing that the original contractor was to have completed
<br />in his contract. The original contractor will not be paid the
<br />full amount of the contract obviously, so he will be taking
<br />the loss on the portion the other contractor is completing.
<br />This has been under negotiation for some time.
<br />The vote for the approval of the above Change Order was unani-
<br />mous and motion was carried.
<br />e.
<br />Change Order No. 1 to Rehabilitation Contract No. SECD /PR /CS -2/21, CHANGE
<br />Southeast Community Development Housing Program: Approval was ORDER 1
<br />requested of this Change Order, for a decrease in contract amount TO REHAB
<br />of $40.00, with Fleming Masonry Construction Company, (Contract: CONTRACT
<br />$3,975.00), or an amended contract total of $3,935.00, with con- SECD /PR /CS-
<br />tract time unchanged, for rehabilitation work at: 707 E. Indiana 2/21 AP-
<br />Avenue, in the Southeast Community Development Housing Program. PROVED,
<br />SECD HOUSIN,
<br />Mr. Brownell read Mr. Kenneth J. Schaller, Project Engineer's PROGRAM
<br />memorandum, which states that the homeowner is having additional
<br />work performed on the exterior of her home and prefers to have
<br />those individuals scrape and paint her gutters and downspouts.
<br />The work the homeowner is having completed does not conflict
<br />with the contract specifications. This work totals $40.00 and
<br />would be deleted from the contract amount, reducing the contract
<br />amount to $3,935.00. Staff recommends the Change Order for ap-
<br />proval.
<br />Motion was made by Mr. Wiggins, seconded by Mr. Cira and carried,
<br />for the approval of Change Order No. 1 to the above Contract,
<br />for a decrease in contract amount of $40.00, or an amended con-
<br />tract total of $3,935.00, in the Southeast Community Development
<br />Housing Program.
<br />f. Change Order No. 1 to Rehabilitation Contract No. SECD /PR /CS -3/23, CHANGE
<br />Southeast Community Development Housing Program: Approval was ORDER 1
<br />requested of this Change Order, for an increase in contract amount TO REHAB
<br />of $396.00, with Area Services, Inc., Contract: $7,276.00), or CONTRACT
<br />an amended contract total of $7,672.00, with contract time un- SECD /PR /CS-
<br />changed, for rehabilitation work at: 407 E. Ohio Street, in the 3/23 AP
<br />Southeast Community Development Housing Program. PROVED,
<br />SECD HOUSING
<br />The specifications called for painting of the walls in the bath PROGRAM
<br />room. However, because of the present condition of the walls and
<br />also the type of covering on the walls, the contractor recommends
<br />- 7 -