6. NEW BUSINESS (Cont'd
<br />trical subcontractor .concerning -an upcoming change order relating
<br />to the contract. Per Mr. Richard E. Pfeifer's memorandum, (who is
<br />Chief Inspector of the Northwest Bureau of Housing), if this time
<br />extension is approved, the contractor states he can complete this
<br />structure within the specified time limit.
<br />Mr. Keith P. Crighton, Director, Bureau of Housing, added he had
<br />no other comments, other than Slatile has been performing reason-
<br />ably well, and that he is trying to be as flexible as possible
<br />with his subcontractor. The subcontractor had jury duty for two
<br />weeks this month and lost that time. One house is involved on
<br />this contract.
<br />Mr. Wiggins moved for the approval of Change Order No. 2 to Re-
<br />habilitation Contract No. NWCD /03, with Slatile Roofing & Sheet
<br />Metal, Inc., for an extension in contract time from May 21, 1976,
<br />to June 30, 1976, with no change in contract amount, in the North-
<br />west Community Development Program. Motion was seconded by Mr.
<br />Donaldson.
<br />Mr. Richard Pfeifer in his memorandum advised that the specifica-
<br />tion called for the installation of 100 amp service with circuit
<br />breakers. It was brought to his attention by the electrical con-
<br />tractor that this structure already has 100 amp service that is
<br />in good working order. However, the structure does not meet our
<br />project specifications; i.e., insufficient plugs, lights, switches,
<br />ground fault installations. This electrical work totals $690.00,
<br />leaving a balance of $123.00 that was in the original specifica-
<br />tion for the electrical system work in amount of $813.00. Staff
<br />feels this balance should be applied to the insulation and enclos-
<br />ing of the east wall in the utility room, and recommends the con-
<br />tract be amended to include the items on the change order and it
<br />be approved. The additions include 19 items amounting to: $813.00.
<br />Motion was made by Mr. Robinson that we grant his request, seconded
<br />by Mr. Wiggins and carried, for the approval of Change Order No. 3
<br />to Rehabilitation Contract No. NWCD /03, with Slatile Roofing & Sheet
<br />Metal, Inc., with no changes in time or contract amount, in the
<br />Northwest Community Development Program.
<br />- 5 -
<br />31
<br />Commissioner Robinson said he can't see why it would take six
<br />weeks - -even if he would have to go and get a new electrical con-
<br />tractor- -why he needs six weeks extension just to do electrical
<br />work in a house. Commissioner Wiggins said he has already had
<br />most of the extension time; he only has two weeks left. Motion
<br />carried.
<br />d.
<br />Change Order No. 3 to Rehabilitation Contract No. NWCD /03, North- CHANGE
<br />west Community Development Program: Commission approval was re- ORDER NO.
<br />quested of this Change Order, with Slatile Roofing & Sheet Metal, TO REHAB.
<br />Inc., which also relates to the above Contract item, for changes CONTRACT
<br />in specification items with no changes in time or contract amount, NWCD /03
<br />for rehabilitation work at 506 LaPorte Avenue, in the Northwest APPROVED,
<br />Community Development Program. NWCD PROG
<br />Mr. Richard Pfeifer in his memorandum advised that the specifica-
<br />tion called for the installation of 100 amp service with circuit
<br />breakers. It was brought to his attention by the electrical con-
<br />tractor that this structure already has 100 amp service that is
<br />in good working order. However, the structure does not meet our
<br />project specifications; i.e., insufficient plugs, lights, switches,
<br />ground fault installations. This electrical work totals $690.00,
<br />leaving a balance of $123.00 that was in the original specifica-
<br />tion for the electrical system work in amount of $813.00. Staff
<br />feels this balance should be applied to the insulation and enclos-
<br />ing of the east wall in the utility room, and recommends the con-
<br />tract be amended to include the items on the change order and it
<br />be approved. The additions include 19 items amounting to: $813.00.
<br />Motion was made by Mr. Robinson that we grant his request, seconded
<br />by Mr. Wiggins and carried, for the approval of Change Order No. 3
<br />to Rehabilitation Contract No. NWCD /03, with Slatile Roofing & Sheet
<br />Metal, Inc., with no changes in time or contract amount, in the
<br />Northwest Community Development Program.