6. NEW BUSINESS (Cont'd
<br />The additional amount of money is the difference between
<br />an increase of $43,637.44 and a decrease of $38,438.50,
<br />leaving the balance to be added to the Contract. An
<br />extension of 32 calendar days is also requested for comple-
<br />tion of this work.
<br />On motion by Mr. Chenney, seconded by Mr. Wiggins and unani-
<br />mously carried, Change Order No. 2 to Phase II -C, in the
<br />amount of $5,198.94 and an extension of time of 32 calendar
<br />days, was approved.
<br />Improvements:
<br />Change Order No. 9
<br />Approval of
<br />ement Contracts A, B,
<br />to Contracts A, B, C and D, Site
<br />this Change Order No. 9 to Site
<br />C and D, in the Northeast Code
<br />CHANGE ORDER NO. 9
<br />TO CONTRACTS A, B, C
<br />& D, SITE IMPROVEMENTS,
<br />Impro
<br />Enforcement
<br />Project E -3 was
<br />requested, which is for an ex-
<br />APPROVED, E -3
<br />tensi
<br />n of time to August 24, 1973, with the Rieth -Riley
<br />Const
<br />uction Co., Inc.
<br />The weather last fall and this spring did not permit suffi-
<br />cient working days to complete in accordance with the contract.
<br />Also, placing Sorin Street as a revision in the contract re-
<br />vised the scheduling of removal and curb construction which
<br />affected the subcontract work. Mr. Patrick McMahon, Manager
<br />of Bureau of Public Construction, agrees this request is
<br />reasonable.
<br />On motion by Mr. Wiggins, seconded by Mr. Chenney and unani-
<br />mously carried, Change Order No. 9 to Contracts A, B, C and
<br />D, was approved for an extension of time to August 24, 1973.
<br />h. Change Order No. 1 to Contract No. 5, Phase III: CHANGE ORDER NO. 1
<br />Approval was requested of this Change Order with a ickey TO CONTRACT NO. 5,
<br />Co., Inc., for a decrease in contract amount of $104,000.00, PHASE III, PEDESTRIAN
<br />R -66 Project. WAY, APPROVED, R -66
<br />Due to a misunderstanding in the contract bidding, the Hasting's
<br />Paving Company, a subcontractor to The Hickey Company, is pass-
<br />ing a credit to the Owner in amount of $39,000 in Part "A" of
<br />Contract No. 5. A further credit to the Owner in amount of
<br />$65,000 for performing work in detail: The Hickey Company
<br />Will s blet only the flat brick paving to the Hastings Company,
<br />all in accordance with Section 262, and The Hickey Company will
<br />take over the work of the brick edging, copings, and walls in
<br />accordance with the balance of Section 262, at the same time
<br />purchasing the specified materials from the Hastings Company,
<br />with a total savings to the Department of Redevelopment of
<br />$104,000.00.
<br />On motion by Rev. Williams, seconded by Mr. Chenney and unani-
<br />mously carried, Change Order No. 1 to Contract No. 5, Phase
<br />III, was approved for a decrease in contract amount of
<br />$104,000.00.
<br />9
<br />
|