Contract No:R -39514 <br />Change Order No:002 <br />Contract: <br />Project: <br />Change Order Nbr: <br />INDIANA <br />Department of Transportation <br />R -39514 <br />State: 160007600LC4 <br />002 <br />Date:10/07/2019 <br />Page: 3 <br />Change Order Description: Time Extension <br />Reason Code: SCOPE CHANGES, Added Quantities/Items <br />CLN PCN PLN Item Code Unit Unit Price O pity. � Comment���i�mount Change �� „ ���� � ���� <br />Total Value for Change Order 002 m $ 0.00 <br />Milestone Time Adjustment <br />MileStone Nbr: 02 <br />Milestone Description: INTERMEDIATE COMPLETION DATE <br />Original Completion dt: 08/16/2019 Adj comp) dt 09127/2019 Adj No. of Days 36 <br />Explanation: Towards the end of the project I mentioned to the City that several pay itunis underran, and the project would be under <br />the original amount. Upon i speaking with Kyle, City of South Bond Engineer, Kyle mentioned during the design phase <br />there was several sections of sidewalk which needed to be removed doe to safety hazards, but because of funding the <br />city had to remove those sections of sidewalk from the project„ Kyle mentioned the section of sidewalk on the right side <br />of Olive between Bulla and Elwood, and along the right side of Brookfield just south of Borgan were last to get removed . <br />Kyle mentioned since the project underran and those sections were going to be in the original plans the city would like to <br />add those sections of sidewalk to the current project, The project is currently under the original contract amount by <br />60,000 dollars. The additional work would roughly cost around 15,000 dollars factoring in all construction. This amount <br />reflects all contract prices still apply and no addhltonaf payment will be made over these original dams, will be paid for the <br />additional work. After subtracting that amount tine project should still' be around 45,000 dollars under the original amount„ <br />I spoke to Ryan Forgey INDOT AE, regarding the city wanting to add, additional sidewalk removal and' replacement to the <br />project. Ryan stated he would need to contact the FHWA to make sure it wouid'be OK Ryan slated he received an email <br />back from the FHWA stating they were OK with adding the additional ;sidewalk to the project. To perform this extra. work <br />Rieth Riley would need extra days be added to the intermediate completion date of the project, The project has an <br />intermediates completion data of Aug 22, 2019. The additional worts was first proposed on Aug 22, 201f9 We ,got the OK <br />from FHWA to perform the work on Aug 28, 2019, Which equals 6 days. Rlot'h Rhloy would not have any crews available <br />until September 23, 2019 which equals 14 days. Rieth Riley Is stating they would need around 5 days to complete all the <br />additional work. Adding up all the days needed it comes to 36 days. Adding 36 days to the intermediate completion data <br />of August 22, 2019 that would make the new intermediate completion date of September 27, 2019. This change order is <br />created to address the additional days needed to perform the additional work. <br />Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. <br />General or Standard Change Order Explanation <br />'Towards the and of the project t mentioned to the Cary that severed pay, 'Items underran, and the project would be undor the original ,amount. Upon <br />speaking wilh Kyle, City of South Bernd Engineer, kyle mentioned during the design phase there was several sections of sidewalk which needed <br />to be removed due to safety, hazards, but because of funding the city had to remove those sections oil sidewalk, from the project. Kyle mentioned <br />the section of sidewalk on the right side of Olive between Buifa and Elwood, and along the right side of Brooklield just south at Bergen were lest. <br />to get removed . Kyle mentioned since the project underran sand those sections were going to he in the original plans, the city would like to add <br />those sections of sidewalk to the current project, Tire project Is currently under the original contract amount by 60,000 dollars. The additional <br />work would roughly cost around 15,000 dollars factoring In all construction. This amount reelects all contract prices still apply arid no additional <br />payment will be invade over these original Items, will be paid for the additional work, After subtracting that amount the project should still be <br />around 45,000 doitars under the original amount, f spoke to Ryan Forgey INDOTAE, regarding the city wanting to add additional sidewalk <br />removal and replacemenl to the project. Ryanstated he would need to contact the FHWA to make sure It would be OK. Ryan stated lie received <br />an ernall track from the FHWA slating they were OK with adding the additional sidewalk to the project. To perform this extra work Rielb Riley <br />would need extra days be added to the intermediate completion date of the project, 'rho project has ail intermediate completion date of Aug 22, <br />2019. The additional work was first proposed on Aug 22„ 2019. We got the OK frorn FHWA to perform the work on Aug 28„ 2019. Which equals 6' <br />days Rielh Riley would not have any crews available until September 23, 2019 which equals 14 days = Riieth Riley is stating they would need <br />around 5 days to complole all the additional work. Addling up all tine days needed it comes to 36 days. Adding 36 days to the intounediate <br />completion date of August 22, 2019 that would make the new intermediate completion date of September 27, 2019. This change order is created <br />to address the additional days needed to perform the additional work. <br />Change Order Explanation for Specific Line Item <br />...........................................................................................................I................ <br />It is the intent of the parties that this change order is full and complete compensation for the work describe above <br />Notification and consentt to this change order is hereby acknowledged. ✓ `` <br />jr '.. Signed <br />Contractor _ ..� <br />Date: h ,� 7q <br />._.. .._...� ._ <br />