Contract No:R -39513 INDIANA Date:11/06/2018 <br />Change Order No:004 Department of Transportation Page: 3 <br />Contract: R -39513 <br />Project: 1500075 - State: 160007500LC4 <br />Change Order Nbr: 004 <br />Change Order Description: Overruns and Underruns in excess of $20,000.00 <br />Reason Code: CHANGED COND, Constructability Related <br />... r. ��. P „. le'l 6 w „Y11 s. "d -. "e e..... <br />CLN PCN PLN Item Code Unit Unit Price CO t]ty Comment Amount Change <br />0023 1600075 0023 604-06070 SYS 45.900 907.010 C Amount:$ 41,631.75 <br />Item Description: SIDEWALK, CONCRETE <br />Supplemental Descriptlonl: <br />Supplemental Description2: <br />0024 1600075 0024 604-08086 SYS 122.750-550.350 C Amount:$-67.555.46 <br />Item Description: CURB RAMP, CONCRETE <br />Supplemental Descriptlonl: <br />Supplemental Description2: <br />0026 1600075 0026 605-06120 LIFT 37.850 1113,500 C Amount.$ 42,145.97 <br />Item Description: CURB, CONCRETE <br />Supplemental Descripflonl: <br />Supplemental Descriptlon2: <br />Total Value for Change Order 004 - $ 16,222.27 <br />Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. <br />General or Standard Change Order Explanation <br />The sidewalk hem overran because additional walk was removed at several locations that was In poor condition and impossible to match or at <br />curb romp locations in order to meet the required ADA slopes. Also the breakdown between curb ramps and sidewalk at the comers was not <br />calculated per ADA standards In the designer talcs causing a substantial overrun of plan quantity In the sidewalk and underrun in the curb <br />ramps. The curb ramp item underran because of the same reason mentioned above regarding an error In the designer calce with the breakdown <br />between sidewalk and curb ramps at the comer not done per ADA standards. The curb quantity overran because more curb removal was done <br />than shown because it had been paved over and not Included In the designer quantity tales. More removal means more new curb. Also the <br />owner requested curb at the radius comers to be uniform at all 4 comers which was not always shown that way on fhe plans. There is no <br />additional time required for this change order. <br />Change Order Explanation for Specific Line Item <br />It is the Intent of the parties that this change order Is full and complete compensation for the work describe above. <br />Notification and consent to this change order Is hereby acknowledged. <br />Contractor: _".9..r;�rl CO ,t _ Signed By �„µ° <br />Date. 4 <br />NOTE: Other required Stale and FHWA signatures will be obtained electronically through the SileManager system. <br />