EXHIBIT "A" <br />INSPECTION FEE JUSTIFICATION <br />MANHOURS BY CLASSIFICATION <br />OWNER: South Bend, Indiana <br />DESCRIPTION: LaSalle Safe Route to School <br />Contract No. R-39514; Des. No. 1600076 <br />LETTING: <br />NOTICE TO PROCEED: <br />EARLIEST DATE TO BEGIN WORK: <br />INTERMEDIATE COMPLETION DATE: <br />COMPLETION DATE: <br />PRECONSTRUCTION ACTIVITIES: <br />CONSTRUCTION ACTIVITIES: <br />POST -CONSTRUCTION ACTIVITIES: <br />October 11, 2018 <br />November 26, 2018 <br />March 1, 2019 <br />August 16, 2019 <br />April 30, 2020 <br />Anticipated <br />2/25/2019 to 3/2/2019 = 1.00 weeks <br />3/4/2019 to 8/16/2019 = 24.00 weeks <br />8/19/2019 to 4/25/2020 = 36.00 weeks <br />61.00 weeks <br />The following pages (manhour justification and fee estimate) are based on the above construction schedule. Any delay or extension <br />in the construction that significantly extends the completion date shown above may require an extension to this Agreement <br />and an increase in the estimated fees. <br />8/1/2018 <br />