BID/PROPOSAL
<br />CITY OF SOUTH BEND
<br />Project Name Miami Basin Drainage Improvement Project
<br />Project No.
<br />For Bids Due
<br />BASE BID
<br />116-082C
<br />July 24, 2018
<br />Item
<br />No.
<br />Description
<br />Quantity
<br />Unit
<br />Unit Price
<br />Total Amount
<br />1
<br />Mobilization and Demobilization
<br />1
<br />LS
<br />$ 166,125.00
<br />$ 166,125.00
<br />2
<br />Clear Right of Way
<br />1
<br />LS
<br />$ 8,006.00
<br />$ 8,006,00
<br />3
<br />Tree, Remove
<br />7
<br />EACH
<br />$ 867.00
<br />$ 6,069.00
<br />4
<br />Gate, Remove
<br />2
<br />EACH
<br />$ 255.00
<br />$ 510.00
<br />5
<br />Concrete Drive, Remove
<br />2
<br />EACH
<br />$ 1,733.00
<br />$ 3,466.00
<br />6
<br />Sidewalk, Remove
<br />95
<br />SYS
<br />$ 16.00
<br />$ 1,520.00
<br />7
<br />Curb, Remove
<br />183
<br />LFT
<br />$ 11.00
<br />$ 2,013.00
<br />g
<br />Excavation, Common
<br />280
<br />CYS
<br />$ 49.00
<br />$ 13,720.00
<br />9
<br />Borrow
<br />710
<br />CYS
<br />$ 51.00
<br />$ 36,210.00
<br />10
<br />Sediment, Remove
<br />630
<br />CYS
<br />$ 125.00
<br />$ 78,750.00
<br />11
<br />Water Quality Structure Maintenance
<br />3
<br />EACH
<br />$ 1,020.00
<br />$ 3,060.00
<br />12
<br />Topsoil
<br />242
<br />CYS
<br />$ 54,00
<br />$ 13,068.00
<br />13
<br />No. 2 Stone
<br />140
<br />TON
<br />$ 18.00
<br />$ 2,520.00
<br />14
<br />Temporary Seeding
<br />7,260
<br />SYS
<br />$ 0.33
<br />$ 2,395.80
<br />15
<br />Temporary Silt Fence
<br />540
<br />LFT
<br />$ 2.00
<br />$ 1,080.00
<br />16
<br />Geotextile for Subgrade, Type 1A
<br />1,320
<br />SYS
<br />$ 6,00
<br />$ 7,920.00
<br />17
<br />Compacted Aggregate, No 53
<br />360
<br />TON
<br />$ 41.00
<br />$ 14,760.00
<br />18
<br />HMA Patching, Type A
<br />17
<br />TON
<br />$ 326.00
<br />$ 5,542.00
<br />19
<br />PCCP Pavement, 9 in.
<br />380
<br />SYS
<br />$ 91.00
<br />$ 34,580.00
<br />20
<br />Fence Gate, Cantilevered, 24`
<br />2
<br />EACH
<br />$ 765.00
<br />$ 1,530.00
<br />21
<br />Sidewalk, Concrete
<br />80
<br />SYS
<br />$ 82.00
<br />$ 6,560.00
<br />22
<br />Curb and Gutter, Concrete, Type B
<br />110
<br />LFT
<br />$ 55.00
<br />$ 6,050.00
<br />23
<br />Curb, Integral, Concrete
<br />117
<br />LIFT
<br />$ 52.00
<br />$ 6,084.00
<br />24
<br />Riprap, Class 1
<br />366
<br />TON
<br />$ 103.00
<br />$ 37,698.00
<br />25
<br />Riprap, Revetment
<br />100
<br />TON
<br />$ 104.00
<br />$ 10,400.00
<br />26
<br />Mulched Seeding, U
<br />1,817
<br />SYS
<br />$ 1,00
<br />$ 1,817.00
<br />27
<br />Sodding
<br />357
<br />SYS
<br />$ 13.00
<br />$ 4,641.00
<br />Version 10/17/2017 Contractor's Bid for Public Works —7