Laserfiche WebLink
CITY OF SOUTH BEND, INDIANA <br />DEPARTMENT OF PUBLIC WORKS <br />PROJECT CHANGE ORDER <br />DATE: 2/23/2018 <br />PROJECT NO: 11 7-06OR <br />PROJECT NAME: Newman Center Site Development, Division B and C <br />CONTRACT DATE: 8/2'1/2017 <br />CHANGE ORDER NO: 2 _ _ (Final) <br />SUBJECT OF CHANGE ORDER: PCR #3-Final Quantities <br />All items completed substantially as planned. <br />See attached Comparison of Estimate for overruns and underruns. <br />The original contract sum <br />Net change by previously authorized change orders <br />The contract sum prior to this change order <br />By this Change Order, the project amount is <br />The new contract sum including this change order <br />This Change Order represents a total change of <br />Total change for entire project <br />Original contracted completion date/time <br />Extension of date/time by previous change orders <br />Date/time extension by this change order <br />New completion date/time <br />Matthew D. Cain, President <br />Printed Name and Title <br />HRP Construction Inc. <br />Company Name <br />5777 Cleveland Road, P.O. Box 266 <br />Address <br />South Bend, IN. 46624 <br />City, State, Zip <br />$ 184,353.12 <br />$ 22,403.42 <br />$ 206,756.54 <br />Increased <br />Decreased <br />$ 8,364.16 <br />$ 215,120.70 <br />4,05 % <br />16.69 % <br />.11/14/2017 <br />0 days <br />0 days <br />11/14/2017 <br />RECOMMENDED FOR APPROVAL <br />CONS w <br />ICTION MANAGER <br />CITY OF SOUTH BEND <br />BOARD OF PUBLIC WORKS <br />Approved "Dati�-3 `3 <br />Gary A. g3i&, President <br />Elizabeth A. Maradik, Member <br />Therese J. Ddrau, Member <br />Ja 7's A. Mueller, Member <br />