Laserfiche WebLink
1.) Pemberton Davis Electric can begin work within ten days after award of the project. Work will <br />begin by establishing necessary traffic control. Construction will begin with the demolition of <br />existing sidewalk, installation of conduit as required via directional boring, proceed by installing <br />foundations, and then followed by signal pole and signal equipment installation. The work will <br />finish with the commissioning of the signal and clean-up. We expect a crew of three to four <br />workers during the duration of the project. <br />2.) We anticipate subletting the directional boring, sidewalk and paving work, and pavement <br />marking. Although we have procured quotations for subcontracted work, actual Subcontractors <br />have not yet been chosen. <br />3.) We have digger derricks, bucket trucks, directional boring machines, trenchers, and back hoes at <br />our disposal. <br />4,) We have not entered into any contracts, but have received quotations for materials required on <br />the project. <br />