114-053 <br />WWTP Secondary Treatment Improvements <br />Dewatering Delay Cost Breakdown - Change Order No. 10 <br />Item No. <br />Description <br />Amount <br />1 <br />Temporary Well #3 <br />$ - <br />2 <br />Temporary Well #5 & #6 <br />$ - <br />3 <br />Temporary Well #7 <br />$ - <br />4 <br />Leave Temporary Well 7 In Service <br />$ 13,22550 <br />5 <br />Temporary Well #8 <br />$ - <br />6 <br />Temporary Pumps at RAS Pump Station <br />$ 6,977.00 <br />7 <br />Overtime August -December 2016 <br />$ 49,959.00 <br />8 <br />Management Costs <br />$ 169,412.20 <br />8 <br />Construction Equipment Costs <br />$ 146,596.25 <br />10 <br />Winter Conditions <br />$ 12,723.24 <br />11 <br />Lost Productivity - Winter Work <br />$ 19,000.00 <br />12 <br />Premiums for Electrical Work <br />$ 4,106.81 <br />TOTAL Change Order No. 10 Value <br />$ 422,000.00 <br />Value Agreed upon 06/06/2017---------------- > <br />$422,000.00 <br />