REGULAR MEETING MAY 29, 2001
<br />opened for the above referred to project. Mr. Littrell stated that one discrepancy on the bid received
<br />from Kaser-Spraker Construction Company was found. The mistake is a arithmetical error in the
<br />summation of the extensions. Special Provisions for this project and all recent Public Works
<br />construction projects have included Section III A. Lc which states that the Board reserves the right
<br />to award based upon "the probable final, as constructed cost of the project work." To date, no
<br />customers have come forward for full block curb, sidewalk, or combination curb, sidewalk, and drive
<br />approach replacement so there will be zero units charged for Items la, 2a, and 3a. The quantities
<br />in Items lb, 2b, and 3b will be higher than the initial estimate as given in the proposal. The
<br />proposals based on this information were retabulated, as there will be no full block replacements.
<br />Bidders were also notified in the Special Provision that a contract would not be issued to the same
<br />company for both zones. Selge Construction was the lowest responsive and responsible bidder in
<br />both zones for the probable final cost of the project. They prefer to work in Zone 2. Kaser-Spraker
<br />Construction is the next lowest responsive and responsible bidder for Zone 1. Mr. Littrell
<br />recommended the contracts be awarded to Selge Construction, 2833 South 11' Street, Niles,
<br />Michigan, for $233,075.00 (Zone 2) and to Kaser-Spraker Construction, 25487 West State Road 2,
<br />South Bend, Indiana, for $282,875.00 (Zone 1).
<br />Therefore, Ms. Roemer made a motion that the recommendation be accepted and the bids awarded
<br />as outlined above. Mr. Inks seconded the motion which carried.
<br />APPROVAL OF REQUEST TO ADVERTISE FOR THE RECEIPT OF BIDS - CURB
<br />SIDEWALK AND DRIVE APPROACH REPAIR - SOR1N STREET - PROJECT NO 101-27
<br />In a memorandum to the Board, Mr. Hesham Khalil, Engineering, requested permission to advertise
<br />for the receipt of bids for the above referred to project. Mr. Khalil stated that this project will
<br />construct public works improvements for removal and replacement of curbs, sidewalks and drive
<br />approaches on Sorin Street. Therefore, upon a motion made by Mr. Inks, seconded by Ms. Roemer
<br />and carried, the recommendation was approved.
<br />APPROVE CHANGE ORDER - SOUTHFIELD SOUTHERN STORM SEWER - SECTION I -
<br />YOUNGS EXCAVATING - PROJECT NO.100-59
<br />Ms. Roemer advised that Mr. Toy Villa, Public Construction Manager, has submitted Change Order
<br />No. 1 on behalf of Youngs Excavating, Post Office Box 2766, South Bend, Indiana, indicating that
<br />the Contract amount be decreased $8,498.64 for a new Contract sum including this Change Order
<br />in the amount of $270,290.36. Upon a motion made by Ms. Roemer, seconded by Mr. Inks and
<br />carried, the Change Order was approved.
<br />APPROVE CHANGE ORDER - SOUTHFIELD SOUTHERN STORM SEWER - SECTION I -
<br />YOUNGS EXCAVATING - PROJECT NO.100-59
<br />Ms. Roemer advised that Mr. Toy Villa, Public Construction Manager, has submitted Change Order
<br />No. 2 on behalf of Youngs Excavating, Post Office Box 2766, South Bend, Indiana, indicating that
<br />the Contract amount be increased $8,270.00 for a new Contract sum including this Change Order
<br />in the amount of $278,560.36. Upon a motion made by Ms. Roemer, seconded by Mr. Inks and
<br />carried, the Change Order was approved.
<br />APPROVE CHANGE ORDER - LEIGHTON PLAZA - CAST IN PLACE CONCRETE -
<br />HAGERMAN CONSTRUCTION - PROJECT NO. 97-57-3
<br />Ms. Roemer advised that Mr. Carl Littrell, City Engineer, has submitted Change Order No. 2-03.50-
<br />04 on behalf of Hagerman Construction Corporation, 510 West Washington Boulevard, Fort Wayne,
<br />Indiana, indicating that the Contract amount be decreased $22,719.40 for a new Contract sum
<br />including this Change Order in the amount of $1,047,389.79. Upon a motion made by Ms. Roemer,
<br />seconded by Mr. Inks and carried, the Change Order was approved.
<br />APPROVE CHANGE ORDER - MORRIS PERFORMING ARTS CENTER - RAMENDA
<br />MASONRY - PROJECT NO. 98-25-5.4
<br />Ms. Roemer advised that Mr. Toy Villa, Public Construction Manager, has submitted Change Order
<br />No. 004 on behalf of Ramenda Masonry, 54889 Lexington, South Bend, Indiana, indicating that the
<br />Contract amount be increased $11,015.00 for a new Contract sum including this Change Order in
<br />the amount of $568,042.19. Upon a motion made by Mr. Inks, seconded by Ms. Roemer and carried,
<br />the Change Order was approved.
<br />
|